Permitted Development vs Planning Permission: What’s the Real Difference?
October 26, 2026
Who Grants Planning Permission? Councils, Inspectors and Appeals Explained
October 27, 2026Full planning permission is a planning permission granted on a complete, detailed scheme. The council approves the layout, size, appearance, access and landscaping in one decision, so once any conditions that must be met before work starts have been satisfied, you can build. Outline planning permission is different: it only establishes that the principle of a new building on the site is acceptable, and leaves some or all of the details, known as "reserved matters", to be approved later.
In short, full permission says "you can build this", while outline permission says "something like this could be built here, once you show us the details". This guide explains how each works in England, what the reserved matters are, the time limits that apply and how to decide which route suits your project. If you are new to the terminology, our guide to planning consent, permission and approval is a useful starting point.
What does full planning permission actually approve?
A full application (sometimes called a detailed application) is submitted with everything the council needs to judge the finished development: site and location plans, floor plans, elevations and supporting information about access, drainage, trees, ecology and so on, depending on the scheme. Because nothing is held back, the decision notice approves the development as drawn, usually with conditions attached, for example requiring samples of materials or a construction management plan.
Householder applications for extensions, loft dormers and other alterations to a house are a form of full application. You are asking for permission for a specific, fully drawn design rather than a principle.
Under section 91 of the Town and Country Planning Act 1990, a full permission normally has to be started within three years of the date it is granted, unless the council sets a different period. We cover that deadline, and what counts as starting, in our guide to how long planning permission lasts.
What is outline planning permission?
The Town and Country Planning (Development Management Procedure) (England) Order 2015 defines outline planning permission as a permission "for the erection of a building" granted subject to a condition requiring the council’s later approval of one or more reserved matters. It is therefore a route for new buildings, such as a house on a plot or a housing site, rather than for changes of use or alterations to an existing home.
The reserved matters are any of the following that were not detailed in the outline application:
- Access: how vehicles, cyclists and pedestrians get to and move around the site, including the position of access and circulation routes.
- Appearance: the aspects that determine the visual impression, such as the architecture, materials, decoration, lighting, colour and texture.
- Landscaping: the treatment of the land around the buildings, including screening, planting, earthworks, gardens and boundary treatment.
- Layout: how buildings, routes and open spaces are arranged and orientated in relation to each other and to the surroundings.
- Scale: the height, width and length of each building in relation to its surroundings.
You can reserve all five matters or only some. If access is reserved, the application must still show the area or areas where access points will be. And if the council decides it cannot properly judge the application without some of the details, it must tell you within one month of receiving it and say what further information it needs.
How do full and outline permission compare?
| Full planning permission | Outline planning permission | |
|---|---|---|
| What is approved? | The complete, detailed design | The principle of development, plus any details not reserved |
| Level of detail needed | Full drawings and supporting reports | Less design detail; site plan, description and any matters not reserved |
| Can you start building? | Yes, once pre-commencement conditions are discharged | No, reserved matters must be approved first |
| Time limit (England, by default) | Start within 3 years of the grant | Apply for reserved matters within 3 years; start within 2 years of the final reserved matters approval |
| Council fee, new houses (England, from 1 April 2026) | £610 per house for fewer than 10 houses | £610 per 0.1 hectare for sites under 0.5 hectares, with a further fee for reserved matters |
| Typical use | Self-builds, extensions, most smaller schemes | Establishing land value, testing principle before detailed design, larger phased sites |
The default time limits come from section 92 of the 1990 Act, and councils can set longer or shorter periods in the decision notice, so always read yours. Fees are indexed each April, so check your council’s current fee schedule before you apply.
Why would anyone apply for outline permission?
Outline permission lets a landowner find out whether new development is acceptable in principle without paying for a fully worked-up design first. That is useful when you are deciding whether to buy or sell a plot, when a site’s value depends on whether it can be developed, or when the eventual builder or buyer will want to design the scheme themselves.
The trade-off is time and certainty. Outline permission alone does not let you build anything. You will still need detailed drawings, a further application and another decision period before work can start, and the council will judge the reserved matters on their merits within the framework the outline permission set.
What happens after outline permission is granted?
The next step is one or more reserved matters applications covering the details that were held back. These must be consistent with the outline permission and its conditions. Government guidance says that when reserved matters are approved, the council can only impose conditions that directly relate to those reserved matters. Conditions on other aspects of the development have to be attached when the outline permission is granted.
Reserved matters applications are decided within the usual statutory periods: eight weeks for most applications, or 13 weeks for major developments such as ten or more homes. Once the final reserved matters are approved, the two-year clock to start work runs, alongside any conditions you need to discharge before work begins, including those on drainage and groundworks.
Which route is right for your project?
For a single new house where you already know what you want to build, a full application is usually the more direct route, because you only go through one determination and can start once conditions are cleared. Outline makes more sense where the principle is the main question, or where you want to establish value before committing to design costs.
If you are buying a plot that already has outline permission, check three things early: which matters are reserved, the deadline for submitting them, and any conditions that will shape the design or the build cost. A plot with outline permission close to its reserved matters deadline needs prompt action, or the permission may lapse.
Frequently asked questions
Is a householder application the same as full planning permission?
A householder application is a type of full application for works to a single house, such as an extension. The design is approved in detail, so there is no separate reserved matters stage.
Can I start groundworks with outline permission?
No. Outline permission does not authorise any building work until the reserved matters have been approved and any pre-commencement conditions have been discharged. Starting early risks enforcement action.
Does outline permission expire?
Yes. By default in England, reserved matters must be applied for within three years of the outline grant, and work must start within two years of the final reserved matters approval. The council can set different periods.
Does full planning permission include building regulations approval?
No. Planning permission and building regulations approval are separate. Most new homes and extensions need both, and building control will check the construction itself.
Planning a new build or extension?
CJC Contracts is a Colchester-based building and groundworks contractor, established in 2007 and based in Great Horkesley, working across Essex and Suffolk. Once your permission and details are approved, we can deliver new builds and extensions from groundworks through to completion. For a free quote, visit our contact page or call 01206 273689.
Sources
- Town and Country Planning (Development Management Procedure) (England) Order 2015, article 2 (legislation.gov.uk)
- DMPO 2015, article 5: applications for outline planning permission (legislation.gov.uk)
- Town and Country Planning Act 1990, section 92 (legislation.gov.uk)
- Use of planning conditions (GOV.UK)
- Planning fees: annual indexation from 1 April 2026 (GOV.UK)
- Appeal a planning decision (GOV.UK)