How Long Does Planning Permission Take in the UK? Realistic Timelines
October 24, 2026
What Counts as Starting Work on Planning Permission? Don’t Let Yours Lapse
October 25, 2026In England, full planning permission normally lasts three years from the date on the decision notice: you must begin the development before that date, or the permission expires. Outline permission works differently: you have three years to apply for approval of the reserved matters, then two years from the final approval to start. Once work has lawfully begun, the permission does not run out, even if the build takes longer than three years to finish.
That last point is where most of the confusion lies. The deadline is about starting, not finishing, and “starting” has a legal meaning. This guide explains the time limits for each type of consent, what happens if yours is about to lapse, and how to protect it.
How long does each type of planning consent last?
The default periods are set by law. Section 91 of the Town and Country Planning Act 1990 says every planning permission is granted subject to a condition that development must be begun within “the applicable period”, which in England is three years. The council can set a longer or shorter period if it considers that appropriate, so always read the time-limit condition (usually condition 1) on your own decision notice.
| Type of consent (England) | Default time limit | Where it comes from |
|---|---|---|
| Full planning permission | Begin development within 3 years of the grant | Section 91, TCPA 1990 |
| Outline planning permission | Apply for reserved matters within 3 years of the outline grant, then begin within 2 years of the final reserved matters approval | Section 92, TCPA 1990 |
| Listed building consent | Begin the works within 3 years of the grant | Section 18, Planning (Listed Buildings and Conservation Areas) Act 1990 |
| Building Regulations full plans (applications made after 1 October 2023) | Application ceases to have effect if work has not commenced within 3 years of validation | Building control rules (separate from planning) |
Note the Wales difference: the same section of the Act sets the applicable period at five years in Wales. Everything in this guide refers to England, which covers all our work in Essex and Suffolk.
Does the three years start from when I applied or when it was approved?
From when it was granted. The clock runs from the date on the decision notice, not the date you submitted the application. If you won on appeal, the date the Inspector’s decision was issued is the one that counts. So if your permission is dated 10 March 2026, the default deadline to begin is 9 March 2029.
If you are not sure of the date, you can look the application up on your council’s planning portal. Our guide on how to view planning permission on any property shows where to find the decision notice and conditions.
What do I have to do before the deadline to keep my permission?
You have to lawfully begin the development. Section 56 of the 1990 Act says development is begun when a “material operation” is carried out. The list includes any work of construction in the course of erecting a building, demolition of a building, digging a trench that is to contain the foundations, laying an underground main or pipe to the foundations, and work on laying out or constructing a road.
Two things matter just as much as the physical work:
- Pre-commencement conditions must be discharged first. Many permissions say certain details (materials, drainage, tree protection, a construction management plan) must be approved “before development commences”. Under what lawyers call the Whitley principle, work carried out in breach of a condition that goes to the heart of the permission may not count as a lawful start. Courts have upheld decisions that a permission lapsed for exactly this reason.
- The work must be part of the approved scheme. Digging a trench in the wrong place, or for a different design, will not implement the permission you are trying to keep.
We cover the detail in a separate guide on what counts as starting work on a planning permission. The short version: apply to discharge conditions early, because councils can take weeks to approve the details, and leave a clear margin before the expiry date.
Does planning permission expire if I don’t finish the build?
No. There is no general completion deadline in the Act. Once development has lawfully begun, the permission remains capable of being completed. That is why a lawful start, even a modest one, is valuable.
There are some caveats. The council can, in limited circumstances, serve a completion notice on a development that has started but stalled, and specific conditions on your permission may set their own timescales (for example, landscaping to be planted in the first planting season after occupation). Building Regulations approval is also separate: a building control application can lapse if work has not commenced within three years of validation, so check that side too.
Can I extend planning permission before it runs out?
Not by simply asking for more time. In England, section 73(5) of the 1990 Act specifically prevents councils from using a section 73 application (varying a condition) to extend the time limit for starting development or for submitting reserved matters. Your realistic options are:
- Start lawfully before the deadline, after discharging any pre-commencement conditions.
- Submit a fresh planning application for the same scheme. It will be judged against current local and national policy, which may have changed since your original approval.
- Check whether the work is now permitted development. Some smaller projects may not need a full application at all. Our guide to permitted development rules explains the limits.
Because a new application is assessed afresh, there is no guarantee you will get the same result, which is another reason to plan your start date well ahead of the expiry.
How can I prove my permission has been implemented?
Keep evidence and, if the stakes are high, get it certified. Practical steps include:
- Keep copies of the council’s letters discharging each pre-commencement condition.
- Take dated photographs of the commencement works, such as the excavated foundation trench, with drawings showing where it sits in the approved layout.
- Keep building control records, including the commencement notice and the first inspection.
- Consider applying for a lawful development certificate under section 191 of the 1990 Act. A certificate for existing operations can confirm that works already carried out are lawful, and once issued, that lawfulness is conclusively presumed. This is useful if you plan to pause, sell the site or rely on the permission years later.
Does planning permission transfer if I sell the property?
Yes. Planning permission attaches to the land, not to the person who applied, so a buyer can use an unexpired permission. For buyers in Colchester, Essex and Suffolk, it pays to check the decision date, the time-limit condition and whether any pre-commencement conditions have been discharged before relying on a permission in a valuation or purchase decision.
Frequently asked questions
Is planning permission valid for 3 or 5 years?
In England the default is three years to begin full planning permission. Five years is the default in Wales. Your decision notice may set a different period, so check condition 1.
Can planning permission be renewed after it has expired?
No. Once it has lapsed, you need to make a new planning application, which the council will judge against current policies.
How long do I have to finish building once I’ve started?
There is no general time limit to complete once work has lawfully begun, although a council can serve a completion notice on a stalled development in some circumstances, and individual conditions may set their own timescales.
Does listed building consent last as long as planning permission?
By default, yes: listed building consent works must be begun within three years of the grant, unless the council sets a different period.
Need to make a start before your permission runs out?
CJC Contracts is a Colchester-based building and groundworks contractor, established in 2007 and based in Great Horkesley, working across Essex and Suffolk. We carry out groundworks and foundations, extensions and new builds for homeowners, landlords and developers. Talk to us early about your programme and conditions. For a free quote, visit our contact page or call 01206 273689.
Sources
- Town and Country Planning Act 1990, section 91 (legislation.gov.uk)
- Town and Country Planning Act 1990, section 92 (legislation.gov.uk)
- Town and Country Planning Act 1990, section 56 (legislation.gov.uk)
- Town and Country Planning Act 1990, section 73 (legislation.gov.uk)
- Town and Country Planning Act 1990, section 191 (legislation.gov.uk)
- Planning (Listed Buildings and Conservation Areas) Act 1990, section 18 (legislation.gov.uk)
- Reserved matters (Planning Portal)
- Commencement of work (Building Regulations) (Mid Suffolk District Council)