Can You Start Building While Waiting for Planning Permission?
October 25, 2026
What Is Full Planning Permission? Full vs Outline Explained
October 26, 2026The real difference is who decides. Permitted development is planning permission granted nationally by law for set types of work, so if your project stays within the limits and conditions, you do not need to apply to the council. Planning permission through an application is a decision your council makes on the merits of your particular scheme, after consulting neighbours and weighing local planning policy.
That makes permitted development quicker and cheaper but rigid, and a planning application slower but more flexible. Below we compare the two routes, explain where permitted development rights do not apply, and cover the “middle ground” of prior approval. If you are new to the subject, start with our guide to what permitted development is.
Is permitted development a type of planning permission?
Yes, and that is the point most people miss. Article 3 of the Town and Country Planning (General Permitted Development) (England) Order 2015 says that “planning permission is hereby granted for the classes of development described as permitted development in Schedule 2”. The permission is subject to “any relevant exception, limitation or condition” in each class.
So when people say a rear extension “doesn’t need planning permission”, what they really mean is that it does not need a planning application, because Parliament has already granted the permission, provided every limit is met. Break one limit, even slightly, and the whole project falls outside permitted development and needs an application.
How do the two routes compare in practice?
| Permitted development | Householder planning application | |
|---|---|---|
| Who decides? | The national rules; you check your project against them | Your local planning authority |
| Application needed? | No, except where prior approval is required | Yes, with drawings and forms |
| Council fee in England (from 1 April 2026) | None; optional Lawful Development Certificate at half the normal planning fee; larger home extension prior approval £249 | £548 for alterations or extensions to a single house |
| Design judged on merits? | No, it either meets the limits or it does not | Yes, against local and national policy |
| Neighbours consulted? | Not usually; yes for larger home extension prior approval | Yes |
| Flexibility on size and design | Low, fixed limits | Higher, if the council agrees |
The trade-off is certainty. With an application you get a formal decision notice. With permitted development, nobody checks your interpretation unless you ask. Get it wrong and the work is unauthorised, which can lead to the problems described in our guide to starting work before planning permission.
How can you be sure your project is permitted development?
Government technical guidance says that if you want to be certain a proposed development is lawful, you can apply to your council for a Lawful Development Certificate. For a proposed use or operation, the fee is half of the normal planning application fee. It is not compulsory, but it gives you a formal record that the council accepted the work fell within permitted development.
It is worth considering whenever your design sits close to a limit, such as a projection, height or distance from a boundary. Our article on permitted development myths covers the assumptions that most often trip people up.
When do permitted development rights not apply?
Householder permitted development rights are not available everywhere. According to government guidance, they do not apply, or are more restricted, in these situations:
- Flats and maisonettes. For these rules a “dwellinghouse” does not include buildings containing flats.
- Houses created through certain change-of-use rights, such as some office or agricultural conversions.
- Designated “article 2(3)” land, including conservation areas, National Parks, the Broads, Areas of Outstanding Natural Beauty (now National Landscapes) and World Heritage Sites, where extra restrictions apply.
- Article 4 directions, where the council has removed some or all permitted development rights in an area.
- Conditions on earlier permissions. The original planning permission for your house, or a later one, may have removed permitted development rights.
Listed buildings are a separate case. Works affecting a listed building’s character need listed building consent whether or not planning permission is required.
What is prior approval, and where does it fit?
Prior approval sits between the two routes. The development is still permitted development, but you must notify the council first and it can consider specific matters. The best-known example for homeowners is the larger home extension scheme for single-storey rear extensions.
Under standard permitted development, a single-storey rear extension can project up to 4 metres beyond the original rear wall of a detached house, or 3 metres for other houses, with a maximum height of 4 metres. Outside article 2(3) land and Sites of Special Scientific Interest, the larger home extension scheme raises this to 8 metres for a detached house and 6 metres for other houses. Neighbours are consulted, and work cannot start until the council responds or 42 days have passed.
The government’s householder technical guidance was last updated in September 2019, and the underlying order has been amended since, so always check the current rules or ask your council before relying on a specific limit.
Which route should you choose?
- Clearly within limits: permitted development is usually the simplest route. Consider a Lawful Development Certificate for peace of mind.
- Close to a limit or in a designated area: get the rules checked carefully, and consider a certificate or pre-application advice before you commit.
- You want more space or a different design than permitted development allows: a planning application lets the council judge the scheme on its merits. See our checklist of what needs planning permission.
Whichever route you take, building regulations are a separate requirement. Permitted development does not remove the need for structural, fire safety, insulation and drainage approval.
Are permitted development rights restricted in Essex?
Some are. Colchester City Council, for example, has approved an Article 4 direction for the Mill Field Estate Conservation Area. Its effect is “to withdraw certain of the permitted development rights”, so works such as extending or altering a house, changing a roof, adding a porch, building domestic outbuildings, putting up gates, fences or walls, and even painting outside surfaces need planning permission there. Other Essex and Suffolk councils have their own conservation areas and directions, so check with your council before relying on permitted development.
Frequently asked questions
Is permitted development quicker than planning permission?
Usually, because there is no application to wait for. A Lawful Development Certificate or prior approval adds a waiting period, and for larger home extensions you cannot start until the council responds or 42 days have passed.
Can I use permitted development if I live in a flat?
Not for the householder extension rights. They apply to houses, and government guidance says a dwellinghouse for these purposes does not include buildings containing flats.
How do I know if my permitted development rights have been removed?
Check the planning history of your property for conditions removing them, and ask your council whether an Article 4 direction covers your street. Our guide to viewing planning permission on any property shows how to search past decisions.
Can the council refuse permitted development?
It cannot refuse something that genuinely meets the rules, because the permission already exists. Where prior approval is required, the council can consider the matters set out for that type of development, such as the impact on neighbours for larger home extensions.
Planning an extension or alteration?
CJC Contracts is a Colchester-based building and groundworks contractor, established in 2007 and based in Great Horkesley, working across Essex and Suffolk. Whether your project is permitted development or needs a full application, we build extensions and carry out renovations to the approved plans. For a free quote, visit our contact page or call 01206 273689.
Sources
- Town and Country Planning (General Permitted Development) (England) Order 2015, article 3 (legislation.gov.uk)
- Permitted development rights for householders: technical guidance (GOV.UK)
- Planning fees from 1 April 2026 (Bradford Council)
- Planning application fees (Fylde Council)
- Mill Field Estate Conservation Area (Colchester City Council)