How Long Does Planning Permission Last? The Deadline to Start Work
October 24, 2026
Can You Start Building While Waiting for Planning Permission?
October 25, 2026Starting work on a planning permission means carrying out a “material operation” that forms part of the approved development, such as digging a foundation trench, laying a drain to the foundations, demolishing a building or starting construction of an access road. It must be done before the permission’s time limit expires, and only after any pre-commencement conditions have been discharged. Get either part wrong and the permission can lapse even though there is a hole in the ground.
Full planning permission in England normally has to be begun within three years of the grant (see our guide on how long planning permission lasts). Here is what the law counts as a start, what does not, and the paperwork that keeps your permission safe.
What does the law say counts as starting development?
Section 56 of the Town and Country Planning Act 1990 says development is taken to be begun on the earliest date on which a material operation comprised in the development begins to be carried out. It lists what a material operation is:
- any work of construction in the course of the erection of a building;
- any work of demolition of a building;
- the digging of a trench which is to contain the foundations, or part of the foundations, of a building;
- the laying of any underground main or pipe to the foundations, or part of the foundations, of a building or to such a trench;
- any operation in the course of laying out or constructing a road or part of a road;
- any change in the use of land which constitutes material development.
The bar is low: one foundation trench can be enough. But the operation must be “comprised in the development”, meaning it has to be part of the scheme that was actually approved, in the location shown on the approved drawings.
What usually does not count as a start?
Work that is preparatory, unrelated to the approved scheme, or done in breach of conditions is risky. Common examples:
| Activity | Likely to count? | Why |
|---|---|---|
| Digging a foundation trench in the approved position | Yes, if conditions are discharged | Expressly listed in section 56 |
| Laying a drain or main to the foundations | Yes, if conditions are discharged | Expressly listed in section 56 |
| Demolishing a building that the permission covers | Yes, if conditions are discharged | Demolition is listed in section 56 |
| Starting to construct the approved access road | Yes, if conditions are discharged | Road works are listed in section 56 |
| Soil surveys, trial pits, site clearance or erecting hoarding | Doubtful | Usually investigative or preparatory, not part of the building itself |
| Trench dug before a “before commencement” condition is discharged | Often not | May be unlawful under the Whitley principle (below) |
| Work to a different design or position from the approved plans | No | Not comprised in the approved development |
Why do pre-commencement conditions matter so much?
Because work done in breach of them may not count. Many permissions require details to be approved “prior to the commencement of development”: typical examples are materials samples, surface water drainage, tree protection, contamination surveys and construction management plans.
In the Whitley case (1992) the court held that works carried out in breach of a condition cannot properly be described as commencing the development. Later cases narrowed this: the condition must expressly prevent development starting until it is met and must go to the heart of the permission. That is a judgement made on the facts. In one recent case, an Inspector decided that a condition requiring approval of materials before work began was a true condition precedent, so the works did not lawfully commence and the permission lapsed, and the High Court upheld that decision.
The safe approach is simple: discharge every pre-commencement condition, get the council’s written approval, and only then start. Discharge applications take time, so submit them months before your deadline, not weeks.
Is “starting” for planning the same as “starting” for Building Regulations?
No, and mixing them up is a common mistake. Building Regulations have their own commencement rules. For building control applications made after 1 October 2023, work on a non-complex building or horizontal extension only counts as commenced once the sub-surface structure is complete, including all foundations, any basement and the ground floor structure. For other work, it is when the work the client has identified as 15% of the project is done. You must notify building control within five days of reaching that point, and an application ceases to have effect if work has not commenced within three years of validation.
So a single foundation trench might keep your planning permission alive while doing nothing for your Building Regulations application. Check both timetables.
Do I need to tell anyone before I start?
Often, yes:
- Building control: tell your building control body when work starts and book the first inspection, usually at foundation or drainage stage.
- Community Infrastructure Levy (CIL): where your council charges CIL and the development is liable, a commencement notice must be submitted before work starts. Missing it can be costly. For example, for self-build exemptions where the liability notice was issued on or after 1 September 2019, councils can impose a surcharge of up to £2,500 if the notice is not submitted. Check your council’s CIL pages and any liability notice you have received.
- Your decision notice: some permissions include a condition requiring you to notify the council of the start date. Read every condition.
How do I prove I started in time?
Build an evidence file at the time, not years later:
- Keep the council’s written approval of every pre-commencement condition.
- Photograph the works with dates, ideally with a fixed reference point visible, and mark the trench or drain on a copy of the approved site plan.
- Keep your contractor’s invoices, day sheets and any building control inspection records.
- If you will pause the build, sell the site or rely on the permission later, consider a lawful development certificate under section 191 of the 1990 Act. A certificate for existing operations confirms that works carried out are lawful, and once issued that is conclusively presumed.
Some councils will also confirm informally in writing that they consider a permission implemented, but a certificate carries legal weight that a letter does not.
What if I have missed the deadline?
If the time limit has passed without a lawful start, the permission has expired. In England, a section 73 application cannot be used to extend the time limit for starting development, so the usual route is a fresh planning application, judged against current policy. Our guide on how long planning permission takes sets out realistic timescales for a new decision.
Frequently asked questions
Does digging one trench really keep planning permission alive?
It can. Section 56 lists digging a foundation trench as a material operation. It must be part of the approved scheme and carried out after any pre-commencement conditions have been discharged.
Does site clearance count as starting work?
Generally it is treated as preparatory rather than a material operation. Do not rely on clearance, surveys or hoarding alone to implement a permission.
Can I start work before the council discharges my conditions?
Not if the condition says details must be approved before development commences. Work in breach may be unlawful, open to enforcement, and may not count as a lawful start.
Once I’ve started, do I have to keep working?
There is no general completion deadline once a permission has been lawfully implemented, but councils can serve a completion notice on stalled development in some circumstances, and Building Regulations have separate rules.
Ready to make a lawful start on site?
CJC Contracts is a Colchester-based building and groundworks contractor, established in 2007 and based in Great Horkesley, working across Essex and Suffolk. From groundworks and drainage to complete new builds, we can help you plan the first works around your conditions and deadlines. For a free quote, visit our contact page or call 01206 273689.
Sources
- Town and Country Planning Act 1990, section 56 (legislation.gov.uk)
- Town and Country Planning Act 1990, section 91 (legislation.gov.uk)
- Town and Country Planning Act 1990, section 73 (legislation.gov.uk)
- Town and Country Planning Act 1990, section 191 (legislation.gov.uk)
- Unlawful commencement of development (Shepherd and Wedderburn)
- Pre-commencement conditions and the Whitley principle (Walker Morris)
- Commencement of work (Building Regulations) (Mid Suffolk District Council)
- CIL self-build exemption (Cheshire West and Chester Council)