October 26, 2026You can physically start building before planning permission is granted, but you do it entirely at your own risk. If the application is refused, or approved with changes or conditions your work doesn’t meet, the council can require you to alter or remove what you have built, and ignoring an enforcement notice is a criminal offence. For almost every homeowner the sensible answer is to wait for the decision and use the waiting time to get everything else ready.
A householder application is normally decided within about eight weeks (see how long planning permission takes). Below we explain where the legal line sits, what councils can do if you jump the gun, and the jobs you can safely get on with in the meantime.
Is it illegal to start building before planning permission is granted?
Usually not in itself. Government guidance defines a breach of planning control as including “the carrying out of development without the required planning permission”, and a breach is dealt with through the enforcement system rather than as an immediate crime. The offence comes later: it is an offence not to comply with an enforcement notice once its compliance period has passed and no appeal is outstanding.
There are important exceptions. Altering, extending or demolishing a listed building in a way that affects its character without listed building consent is a criminal offence under the Planning (Listed Buildings and Conservation Areas) Act 1990, whether or not you have applied. And if your project genuinely falls within permitted development, you may not need a planning application at all, so it is worth checking before you assume you have to wait.
What can the council do if you start before a decision?
Councils have a range of tools. Which one they use depends on how serious the breach is and whether the work is likely to be acceptable.
| Power | What it does |
|---|---|
| Enforcement warning notice | Used where unauthorised development has a reasonable prospect of being acceptable. It invites you to submit an application to regularise the work. There is no right of appeal against it. |
| Enforcement notice | Requires specified steps, which can include putting things back as they were. Failing to comply after the compliance period is an offence. |
| Stop notice | Served alongside an enforcement notice to halt an activity. It normally takes effect no sooner than 3 days and no later than 28 days after service. |
| Temporary stop notice | Takes effect immediately to stop work, and expires 56 days after it is displayed on site. |
The time limits for enforcement have also changed. For building work substantially completed on or after 25 April 2024, councils in England have 10 years to take action, rather than the old four years. Waiting it out is not a realistic plan.
What happens to the work if permission is refused?
If the council refuses the application, anything you have built is unauthorised. The Planning Portal warns that where retrospective permission is refused, the council “can issue an enforcement notice which requires you to put things back as they were”. You may be able to appeal, but you are now arguing for work that already exists, often at a cost far higher than the original build.
Government guidance also says a person who has carried out unauthorised development “has only one opportunity to obtain planning permission after the event”. Since 25 April 2024, if you have already made an application to regularise the work, you cannot then argue on appeal against an enforcement notice that permission should be granted. Our guide to retrospective planning permission explains that process in more detail.
Approval is not always the end of the risk either. Planners often ask for amendments during an application: a lower roof, a smaller footprint, different windows. If you have already built to the original drawings, the approved scheme may not match what is on site.
What if permission is granted with conditions?
Many permissions include pre-commencement conditions: details of materials, drainage, tree protection or a construction management plan that must be approved before any work begins. Starting before those are discharged can mean you are in breach from day one, and in some cases the works may not count as a lawful start of the permission at all. Our guide to what counts as starting work covers why this matters.
Will starting early speed up the decision?
No. The council assesses the application in the usual way, against its local plan and national policy, whether or not you have started. The Planning Portal is clear that being asked to submit a retrospective application “does not mean that planning permission will automatically be granted”. Starting early can also draw complaints from neighbours, which brings closer scrutiny rather than a faster decision.
What can you safely do while you wait for planning permission?
The eight weeks or so of a householder application can be used productively. None of the following involves building anything that needs planning permission:
- Prepare building regulations drawings. Building regulations are a separate approval. Under either a full plans application or a building notice you must give building control a commencement notice at least two working days before starting.
- Get structural calculations done. Beams, foundations and any openings in load-bearing walls will need an engineer’s design.
- Check whether the Party Wall etc. Act 1996 applies if you are building on or near a boundary with a neighbour, and plan the notices.
- Get detailed quotes and agree a start date with your contractor, so you are ready to go once conditions are cleared.
- Plan the groundworks. Find out where drains and services run, and whether your foundations may need to go deeper because of clay soil or nearby trees.
- Prepare information for likely conditions such as materials samples or drainage details, so they can be submitted quickly after approval.
Internal works that affect only the interior of a building, or do not materially affect its external appearance, are generally not “development” needing planning permission. They may still need building regulations approval, and listed buildings remain a special case.
How do councils in Essex handle early or unauthorised building work?
Colchester City Council says it will investigate all reported breaches, and that resolving them without formal enforcement action “is often the quickest and most cost-effective option”. It also says formal action will be taken where a breach is serious, where the development cannot be granted planning permission, or where the landowner is unwilling to stop or remove it. Other councils across Essex and Suffolk follow the same national framework, so check your own council’s enforcement policy.
Frequently asked questions
Can I dig the foundations before planning permission comes through?
Digging foundation trenches for a building that needs permission is part of the development itself, so it carries the same risk. If permission is refused or the design changes, you may have to fill them in or redo them, and building control will also want to inspect foundations once work does start.
Does building regulations approval mean I can start?
No. Building regulations deal with how the work is built: structure, fire safety, insulation and drainage. Planning permission deals with whether it can be built at all. You need to satisfy both.
What about a larger rear extension under prior approval?
For the larger home extension scheme, government guidance says work cannot start until the council has responded or 42 days have passed. Starting before then is not covered by permitted development.
Is it a crime to build without planning permission?
Not in most cases. It becomes an offence if you fail to comply with an enforcement notice. Unauthorised works to a listed building are an offence in their own right.
Ready to start as soon as your permission lands?
CJC Contracts is a Colchester-based building and groundworks contractor, established in 2007 and based in Great Horkesley, working across Essex and Suffolk. We can price your extension or groundworks while your application is being decided, so you are ready to make a lawful start once conditions are cleared. For a free quote, visit our contact page or call 01206 273689.
Sources
- Enforcement and post-permission matters (GOV.UK planning practice guidance)
- Retrospective planning permission (Planning Portal)
- Key changes under the Levelling-up and Regeneration Act: planning enforcement (Redditch Borough Council)
- Planning (Listed Buildings and Conservation Areas) Act 1990, section 9 (legislation.gov.uk)
- Permitted development rights for householders: technical guidance (GOV.UK)
- When can I start work? (London Borough of Bromley building control)
- Report a planning breach (Colchester City Council)