What Building Regulations Do I Need for an Extension?
November 4, 2026
CJC Contracts partners with Your Block Management
November 4, 2026The CDM Regulations are the Construction (Design and Management) Regulations 2015, the main UK law for managing health and safety on building projects. They came into force on 6 April 2015 and apply to all construction work, from a kitchen refit to a hospital extension. They set out who must plan, manage and coordinate safety at each stage, and what paperwork is needed before work starts on site.
If you are paying for building work, you are a “client” under CDM, and you have duties too. How much falls on you depends on whether the work is for your own home or for a business.
What do the CDM Regulations actually require?
The Health and Safety Executive (HSE) describes CDM as setting out what people involved in construction need to do to protect themselves from harm and anyone the work affects. In practice, the regulations ask everyone on a project to:
- plan the work so risks are managed from start to finish;
- appoint the right people at the right time;
- cooperate and coordinate with each other;
- share the right information about risks and how they are controlled;
- consult and engage with the workers doing the job.
CDM 2015 replaced CDM 2007, which itself replaced the first CDM Regulations that came into force in 1995. The 2015 version made the client the key player and introduced the “principal designer” role, replacing the old CDM coordinator.
What counts as construction work under CDM?
The definition is wide. Regulation 2 covers building, altering, repairing, maintaining or demolishing a structure; site preparation such as clearance, investigation and excavation; assembling prefabricated elements on site; removing structures and their waste; and installing or maintaining fixed services such as electrics, gas and telecoms.
“Structure” is also broad. It includes buildings, roads and drainage works, and temporary works such as formwork, falsework and scaffolds. So a groundworks package, a drainage repair or a new consumer unit can all be construction work under CDM.
Who are the dutyholders under CDM 2015?
CDM gives specific duties to each party. One person or firm can hold more than one role, as long as they have the skills, knowledge and experience to do it.
| Dutyholder | Who they are | Main duties |
|---|---|---|
| Client | Anyone a project is carried out for | Make suitable arrangements for managing the project, allow enough time and resources, provide pre-construction information, appoint the principal designer and principal contractor where needed |
| Domestic client | A homeowner having work done, not as part of a business | Duties normally pass to the contractor, principal contractor or (by written agreement) the principal designer |
| Designer | Anyone who prepares or modifies designs as part of a business | Eliminate, reduce or control foreseeable risks in building, using and maintaining the structure |
| Principal designer | Designer appointed on projects with more than one contractor | Plan, manage and coordinate health and safety in the pre-construction phase; prepare the health and safety file |
| Principal contractor | Contractor appointed on projects with more than one contractor | Plan, manage and coordinate the construction phase; prepare the construction phase plan; site inductions, security and welfare |
| Contractor | Anyone who carries out, manages or controls construction work | Plan, manage and monitor their own work safely; on single-contractor jobs, prepare a construction phase plan |
| Workers | People working for or under contractors | Look after their own and others’ safety, report danger, cooperate |
What must a commercial client do?
If you commission work as part of a business, for example a landlord, developer, school or facilities manager, regulation 4 puts the full client duties on you. You must:
- make suitable arrangements for managing the project, including enough time and resources, and keep them under review;
- make sure the welfare facilities in Schedule 2 (toilets, washing, drinking water, changing and rest areas) are provided for workers;
- give pre-construction information to designers and contractors as soon as practicable;
- make sure a construction phase plan is drawn up before the construction phase begins;
- make sure the principal designer prepares a health and safety file, keeps it updated and that it is available to anyone who needs it;
- take reasonable steps to make sure the principal designer and principal contractor carry out their duties.
Where there is, or is likely to be, more than one contractor, regulation 5 says you must appoint a principal designer and a principal contractor in writing, as soon as practicable and before construction starts. If you don’t, you take on those duties yourself. If you sell the building, you hand the health and safety file to the new owner.
Do CDM Regulations apply to homeowners?
Yes, CDM applies to domestic projects, but the homeowner’s duties pass to others. HSE defines a domestic client as someone having work done on their own home, or a family member’s home, not as part of a business. Under regulation 7:
- on a single-contractor job, the contractor takes on the client duties;
- with more than one contractor, the principal contractor takes them on;
- alternatively, the homeowner can agree in writing that the principal designer will carry out the client duties.
If a homeowner doesn’t make the appointments, the designer in control of the pre-construction phase becomes the principal designer and the contractor in control of the construction phase becomes the principal contractor. If you do the work yourself as DIY, CDM 2015 does not apply.
For homeowners the practical message is simple: choose a builder who understands CDM and will produce a proportionate construction phase plan before starting. It is part of what you should expect on any domestic project, whether a loft, an extension or a new build.
When does a project need to be notified to HSE?
Every CDM project needs planning and a construction phase plan, but only larger ones must be notified. Under regulation 6, a project is notifiable if the construction work is expected to:
- last longer than 30 working days and have more than 20 workers working at the same time at any point; or
- exceed 500 person days.
HSE says every day on which construction work is likely to happen counts, including weekends and holidays. Notification is made online using form F10 as soon as practicable before construction starts, and the notice must be displayed where workers can read it. A commercial client notifies; on domestic jobs, the contractor, principal contractor or principal designer does it.
What documents does CDM require?
Three documents come up again and again:
- Pre-construction information: what the client knows, or can reasonably find out, about the site and existing building, such as asbestos surveys, services drawings and ground conditions.
- Construction phase plan: the health and safety arrangements and site rules for the job, drawn up before the site is set up. HSE says it should be proportionate; on a small job a simple plan is usually enough.
- Health and safety file: prepared by the principal designer on projects with more than one contractor, holding information needed to carry out future work safely. It is handed to the client at the end.
What happens if CDM is ignored?
HSE can inspect sites, issue improvement and prohibition notices and prosecute serious breaches. Where an inspector finds a material breach, HSE’s Fee for Intervention scheme lets it charge for its time, currently £188 an hour. More importantly, poor planning is how people get hurt: excavations, work at height and unplanned demolition are among the hazards CDM is designed to control.
CDM is separate from Building Regulations, though the language overlaps. Since October 2023, Building Regulations have their own “principal designer” and “principal contractor” dutyholders, responsible for compliance with the regulations rather than site safety. Our guide on whether building control is the same as building regulations explains how that side works.
Frequently asked questions
Does CDM apply to small jobs?
Yes. HSE says CDM 2015 applies to all construction work, including small domestic projects. What changes is the scale of paperwork: a short, proportionate construction phase plan is normally all a small job needs.
Do I need a principal designer for a house extension?
Only if there is, or is likely to be, more than one contractor. As a homeowner, if you don’t appoint one, the designer in control of the pre-construction phase becomes principal designer automatically.
Who pays for CDM compliance?
There is no fee to HSE for following CDM or notifying a project. The cost is in the time spent by designers and contractors on planning, welfare and information, which is normally built into their prices.
Is CDM the same in Scotland and Wales?
CDM 2015 applies across Great Britain. Northern Ireland has its own equivalent regulations.
Talk to CJC Contracts
CJC Contracts is a Colchester-based building and groundworks contractor, established in 2007 and based in Great Horkesley, working on commercial and domestic projects across Essex and Suffolk. If you are planning a project and want a contractor who will plan it safely from day one, get a free quote at cjccontracts.co.uk/contact or call 01206 273689.
Sources
- The Construction (Design and Management) Regulations 2015, legislation.gov.uk
- HSE: Summary of duties for CDM dutyholders
- HSE: Domestic clients
- HSE: CDM 2015 frequently asked questions
- HSE: F10 notification
- HSE: Fees and charges, current rates
- Buckinghamshire Council: contractor responsibilities under Building Regulations