November 9, 2026Only if the work isn’t covered by the Party Wall etc. Act 1996. If it is covered (for example, cutting into a shared wall, building on the boundary line, or digging foundations close to next door), you shouldn’t start until you have served notice, the notice period has run, and you have either your neighbour’s written consent or a surveyor’s party wall award. RICS puts it plainly: you must have an award before you start work under the Act, unless your neighbour has agreed in writing.
Skipping the process isn’t a criminal offence, but it leaves you open to a court injunction, a damages claim and a stalled build. This guide explains which work you can start straight away, what can go wrong if you jump the gun, and what to do if work has already begun. It applies to England and Wales.
Which building work can you start without party wall paperwork?
Plenty of jobs never touch the Act. The GOV.UK explanatory booklet says minor work to a shared wall, such as putting up shelves, fitting recessed electrical sockets or replastering, may not need notice at all. Work set well back from the boundary, and digging that stays outside the distances in section 6, is also outside the Act.
The Act applies to three kinds of work, each with its own minimum notice period:
| Type of work | Section of the Act | Minimum notice |
|---|---|---|
| Building a new wall on or at the boundary line | Section 1 | 1 month |
| Work to an existing party wall or structure (e.g. cutting in steel beams, raising the wall, underpinning) | Section 2 | 2 months |
| Excavating within 3 m of a neighbour’s building and deeper than its foundations, or within 6 m where a 45° line from their foundations would be cut | Section 6 | 1 month |
If your project includes any of these, the notice comes first. Our step-by-step guide on how to serve a party wall notice covers what to include and how to deliver it.
What actually happens if you start without serving notice?
The Act itself has no enforcement procedure for failing to serve notice. Nobody from the council will turn up and fine you. But the GOV.UK booklet is clear that a neighbour can go to court to stop the work with an injunction, or seek other legal redress. RICS warns that a failure to serve required notices may result in legal proceedings against you.
The courts have taken this seriously. In Louis v Sadiq (1997), a homeowner carried out major demolition and rebuilding work affecting a party wall without serving the required notice. His neighbours got an injunction stopping further work, and the Court of Appeal held him liable in nuisance because he had not complied with the party wall legislation. The neighbours’ claim went beyond the physical damage to include losses from not being able to sell their home when planned.
What are the risks nobody mentions?
The legal headline is the injunction, but the practical fallout is often worse:
- A mid-build stop. An injunction can land after the footings are dug or the wall is opened up. Scaffolding, plant hire and trades keep costing money while the site stands still, and an open excavation or propped wall is exposed to the weather.
- No record of your neighbour’s property beforehand. A party wall award usually records the condition of the adjoining property before work begins. Without one, any crack next door becomes your word against theirs.
- Liability beyond the Act. As Louis v Sadiq shows, ignoring the Act can expose you to claims in nuisance, including losses that go well beyond the cost of repairs.
- You usually pay the surveyors anyway. RICS notes that surveyors’ fees normally fall on the building owner who serves notice. Starting early doesn’t avoid that cost; it just adds the risk of legal bills on top.
- A paper trail gap. The GOV.UK booklet advises keeping a copy of any award with your property deeds. A missing award for work that obviously needed one can raise questions later.
- A damaged relationship. You still have to live next door. Neighbours who feel ambushed are far less likely to agree to an early start, access or a single agreed surveyor, all of which save time and money.
Can you start before the notice period runs out?
Yes, but only with your neighbour’s written agreement. The GOV.UK booklet says work can start earlier than the one or two months if the adjoining owner agrees in writing. A friendly chat over the fence isn’t enough.
Timing works the other way too. The booklet says a notice is only valid for a year, so don’t serve it too long before you plan to start. Under sections 3 and 6 of the Act, a party structure or excavation notice ceases to have effect if the work hasn’t begun within twelve months of service and isn’t prosecuted with due diligence.
What if your neighbour doesn’t reply to the notice?
For section 2 and section 6 work, silence isn’t consent. If your neighbour doesn’t agree in writing within 14 days, a dispute is treated as having arisen, and the surveyor process starts. Either you both agree on one surveyor, or you each appoint your own and the two of them pick a third if needed. If your neighbour refuses or fails to appoint anyone, the Act lets you appoint a surveyor on their behalf.
For a new wall at the boundary under section 1, the result is different: if your neighbour doesn’t consent, you must build the wall wholly on your own land.
Once an award is served, either owner has 14 days to appeal to the county court. After that it is final and binding. If your neighbour is pushing back rather than staying silent, our guide on whether a neighbour can refuse a party wall agreement explains what happens next.
What should you do if work has already started?
If you’re the one building and you’ve realised the work needed notice:
- Stop the work covered by the Act and make the site safe.
- Speak to your neighbour straight away and explain what you’re doing to put it right.
- Serve the correct notice and appoint a party wall surveyor.
- Get legal advice if your neighbour has already threatened court action.
If you’re the neighbour, the RICS advice is to talk first. If work carries on regardless, a solicitor can advise on an injunction. Either way, take dated photos of your property’s current condition.
Not sure whether your job needs any of this? Our guide on when you can skip a party wall agreement walks through the exemptions, and what a party wall agreement costs sets out typical surveyor fees.
Frequently asked questions
Is it illegal to build without a party wall agreement?
Not in the criminal sense. The Act has no enforcement procedure for failing to serve notice. But your neighbour can seek a court injunction and claim for loss or damage, so it is a serious civil risk.
Can my neighbour stop my extension?
They can’t stop work you are entitled to do under the Act, but they can influence how and when it is done through the surveyor process. If you skip the process, they can ask a court to stop the work.
How long before starting work should I serve notice?
At least one month for section 1 and section 6 work, and two months for section 2 work. Notices are only valid for about a year, so don’t serve them too early.
Can I start work as soon as my neighbour signs consent?
Once they’ve consented in writing to the work in your notice, you don’t need surveyors. You still need to wait for the notice period to end unless they have also agreed in writing to an earlier start.
Planning an extension next to a neighbour?
CJC Contracts is a Colchester-based building and groundworks contractor, established in 2007 and based in Great Horkesley, working across Essex and Suffolk. On extensions and groundworks close to a boundary, we build party wall timings into the programme so the site doesn’t stall halfway. For a free quote, contact us or call 01206 273689.