How Far Can I Extend the Back of My House? Rear Extension Limits Explained
October 27, 2026
Is a Two Storey Extension Permitted Development? What the Rules Really Say
October 28, 2026In England, you usually don’t need planning permission for a single-storey rear extension on a house, as long as it meets the permitted development rules: no more than 3 metres deep (4 metres for a detached house), no more than 4 metres high, and eaves no higher than 3 metres within 2 metres of a boundary. You do need permission if the extension is bigger, if the property is a flat or maisonette, or if your house has had its permitted development rights removed.
Even when you don’t need planning permission, you will almost certainly need building regulations approval, and you may need to notify neighbours. Here’s how to check each one.
What rules must a single-storey rear extension meet to avoid planning permission?
A single-storey rear extension is permitted development under Class A of the General Permitted Development Order if it meets all of these conditions, as summarised by the Planning Portal:
- It goes no more than 3 metres beyond the rear wall of the original house, or 4 metres for a detached house.
- It is no more than 4 metres high, and no higher than the highest part of the existing roof.
- Its eaves are no higher than the existing eaves, and no higher than 3 metres if any part is within 2 metres of a boundary.
- Together with other extensions and outbuildings, it covers no more than half the land around the original house.
- It doesn’t include a veranda, balcony or raised platform.
- The outside materials look similar to the existing house.
- It isn’t forward of the principal elevation, or of a side elevation that faces a highway.
Miss any one of them and the whole extension needs planning permission, not just the part that’s over. For how the depth and height are measured, and how earlier extensions count, see how far you can extend the back of your house.
Can I build a bigger single-storey extension without a full application?
Yes. Through the larger home extension prior approval scheme, a single-storey rear extension can go up to 6 metres from the original rear wall of a semi-detached or terraced house, or 8 metres from a detached house, still with a 4-metre height limit.
It isn’t planning permission, but it isn’t automatic either. You notify the council with a description and plan, the council writes to adjoining neighbours, and they have at least 21 days to comment. If a neighbour objects, the council assesses the effect on their amenity. You can start once you have written confirmation, or if 42 days pass without a decision. The fee in England is £249 from 1 April 2026. The scheme isn’t available in conservation areas, other Article 2(3) land or Sites of Special Scientific Interest.
When does a single-storey rear extension always need planning permission?
| Situation | Planning permission needed? | Why |
|---|---|---|
| House, within 3 m / 4 m and 4 m high | Usually not | Permitted development under Class A |
| House, 3–6 m (semi/terrace) or 4–8 m (detached) | Prior approval instead | Larger home extension scheme |
| Flat or maisonette | Yes | Class A only applies to houses |
| Permitted development rights removed by condition | Yes | A condition on the original permission |
| Article 4 direction covering extensions | Yes | Council has withdrawn the rights |
| Listed building | Yes, plus listed building consent | Listed building controls apply |
| Conservation area, beyond 3 m / 4 m | Yes | Larger home extension route not available |
Planning conditions are the one homeowners most often miss. Check the original planning permission for your house on the council’s planning register, which our guide to viewing planning permission on any property explains.
Does a single-storey rear extension need building regulations approval?
Almost always, yes. Planning and building regulations are separate. Planning controls what you build and how it looks; building regulations cover structure, foundations, fire safety, drainage, insulation and ventilation. A permitted development extension still needs building regulations approval through your council’s building control team or a registered building control approver.
The main exception is a small conservatory or similar glazed extension. According to the Planning Portal, it’s generally exempt if it’s at ground level, under 30 square metres, separated from the house by external-quality walls, doors or windows, and has independent heating with its own controls. Any new structural opening into the house, such as removing a back wall, still needs approval.
Do I need to tell my neighbours?
For an ordinary permitted development extension, the council doesn’t notify neighbours. The Party Wall etc. Act 1996 can still apply, though. If you’re building on or near a shared boundary, working on a party wall, or digging foundations below and near your neighbour’s foundations, you must give them notice. GOV.UK advises giving notice between 2 months and a year before work starts. Party wall matters are separate from planning and building regulations, so plan them into your programme early.
Should I get a Lawful Development Certificate?
A Lawful Development Certificate for a proposed use isn’t required, but it’s the council’s formal confirmation that your extension is permitted development. It’s worth having if your design is close to the limits, if you’re unsure whether rights have been removed, or if you want clean paperwork for a future sale. Our planning permission checklist covers other common projects.
What should Colchester, Essex and Suffolk homeowners check?
The rules above apply nationally, but local restrictions are common in this area. Colchester City Council has an Article 4 direction in the Mill Field Estate Conservation Area that requires planning permission for extending or altering a house, and many towns and villages across Essex and Suffolk sit in conservation areas where the larger home extension route isn’t available. Before you commit to a design, search your district council’s planning register and conservation area maps, or ask the council directly.
Frequently asked questions
Can I build a single-storey rear extension up to my neighbour’s boundary?
Planning rules allow it, but if any part is within 2 metres of the boundary the eaves must be no higher than 3 metres. You’ll probably also need to serve a party wall notice.
Is a 4-metre extension on a semi-detached house permitted development?
Not under the standard rules, which allow 3 metres for a semi. You’d need prior approval under the larger home extension scheme, or a planning application if that route isn’t available.
Does a flat roof or pitched roof make a difference?
Not to whether you need permission, as long as the height and eaves limits are met. A flat roof can’t be used as a balcony or roof terrace under permitted development.
What happens if I build without permission when I needed it?
The council can ask you to apply retrospectively and, if permission is refused, take enforcement action. So it’s worth checking before you build.
Planning a rear extension in Essex or Suffolk?
CJC Contracts is a Colchester-based building and groundworks contractor, established in 2007 and based in Great Horkesley, working across Essex and Suffolk. We build single-storey rear extensions and the kitchens that often go in them. Every extension needs a site-specific quote, so request a free quote or call 01206 273689.