What Are Building Regulations? A Plain-English Guide for Homeowners
October 29, 2026
When Did Building Regulations Come Into Force? Why It Matters When You Buy an Older Home
October 30, 2026Building control is the independent checking service that makes sure building work meets the building regulations. In England it’s provided either by your council’s building control team or by a private registered building control approver, who checks the plans, inspects the work on site and issues a completion certificate at the end.
It can stop your project because, since 1 October 2023, councils have had the power to serve compliance notices and stop notices, and they can still require non-compliant work to be altered or taken down up to 10 years after it’s finished. Here’s how it works and how to stay on the right side of it.
Is building control the same as building regulations?
No. Building regulations are the rules: the legal standards for structure, fire safety, drainage, insulation and so on. Building control is the process, and the people, that check your work against those rules. Our plain-English guide to what building regulations are explains the rules themselves.
It’s also separate from planning. A planning officer decides whether you can build something; a building control surveyor checks that it’s built safely. Most extensions need building control approval even when they’re permitted development.
Who provides building control?
For a house extension or conversion you can choose between two types of building control body:
| Building control body | Who they are | Points to know |
|---|---|---|
| Local authority building control | Your council’s in-house team, or a shared service between councils | Can take formal enforcement action. Also handles retrospective (regularisation) applications. |
| Registered building control approver | A private company registered with the Building Safety Regulator | Formerly called approved inspectors. Can’t take enforcement action itself; unresolved work is handed back to the council. |
Since April 2024 the Building Safety Regulator, part of the Health and Safety Executive, has regulated the profession. Individual building inspectors must be registered, and it’s a criminal offence to work as one without registration. A private approver also can’t advise on how to comply on the same project it is checking. For higher-risk buildings, such as tall blocks of flats, the Building Safety Regulator itself is the building control authority.
What does a building control inspector actually check?
Their job is to confirm the work meets the regulations, not to judge the quality of finishes. On a typical extension you can expect:
- **A plan check.** With a full plans application the drawings and structural calculations are checked before work starts.
- **Site inspections at key stages.** The Planning Portal lists stages such as foundations, damp-proof course and drains, where you must notify building control so the work can be seen before it’s covered up.
- **A completion inspection.** Once satisfied, building control issues a completion certificate.
On our sites the foundation inspection is often the one that matters most, because the inspector checks the trench depth and the ground before concrete goes in. On the clay soils common across Essex and Suffolk that can mean digging deeper, especially near trees. It’s one reason building control should be part of your groundworks planning from day one.
When do you need to tell building control?
Since the building control changes of October 2023, councils such as Salford explain the main deadlines like this:
| Notice | Deadline |
|---|---|
| Commencement notice | At least two days before work starts |
| Work “regarded as commenced” | Within five days of reaching that stage |
| Change of client or person carrying out the work | Within 14 days |
| Completion | No more than five days after the work is completed |
Approval doesn’t last forever either. A full plans approval is valid for three years from when the plans were deposited, and if work hasn’t started by then it can be declared of no effect. Planning permission works in a similar way, as our guide to what counts as starting work explains.
How can building control stop your project?
The Building Safety Act 2022 gave building control authorities stronger tools. In the Building Act 1984 there are now four main powers:
- **Compliance notices (section 35B).** These require specific steps to put a breach right within a set period. They can be given for a breach up to 12 months old, and ignoring one is an offence.
- **Stop notices (section 35C).** These stop work from starting or continuing, for example where a compliance notice has been ignored or the breach creates a risk of serious harm. Breaching a stop notice is also an offence.
- **Notices to alter or remove work (section 36).** The council can require non-compliant work to be altered or pulled down, and if the owner hasn’t complied within 28 days it can do the work itself and recover the cost. This notice can be served up to 10 years after completion.
- **Prosecution (section 35).** Contravening building regulations can lead to a fine or, on indictment, up to two years’ imprisonment.
In practice the commonest way building control stops a job is far less dramatic: work is covered before it’s inspected, so it has to be opened up again. Foundations concreted, drains backfilled or steels boxed in before a visit can mean days of delay and extra cost.
What does building control cost?
Fees vary by building control body and project. As an example, Colchester City Council’s charges from 1 April 2026 put a full plans application for an extension of 10 to 40 square metres at £925 including VAT, made up of a £275 plan check and £650 for inspections. A building notice for the same size of extension also comes to £925, and regularisation of work already done is charged at the same level. Private approvers quote individually.
What if work was done without building control?
You can apply to the council for a regularisation certificate. You’ll need plans of the work, and you may have to open up floors, walls or foundations so the inspector can see what was built. Issuing the certificate is at the council’s discretion, and regularisation only covers work carried out on or after 11 November 1985.
Frequently asked questions
Can I choose a private approver instead of the council?
Yes, for most domestic projects. Check the company is registered with the Building Safety Regulator, and remember that unresolved problems can be handed back to the council.
Does building control check the quality of my builder’s work?
Only against the regulations. Inspectors check things like structure, fire safety, insulation and drainage; they don’t snag paintwork, tiling or finishes.
Do I need building control if my installer is in a competent person scheme?
Not for that piece of work. Registered installers of boilers, electrics or windows can self-certify and notify it for you, but the rest of the project still needs building control.
Who should arrange the inspections?
Your builder normally calls building control at each stage, but the responsibility to comply sits with you as the owner too, so ask for the inspection record and completion certificate.
Need a builder who works with building control every week?
CJC Contracts is a Colchester-based building and groundworks contractor, established in 2007 and based in Great Horkesley, working across Essex and Suffolk. We build extensions and handle everything from foundations to drainage. Every project needs a site-specific quote, so request a free quote or call 01206 273689.
Sources
- Planning Portal: Full plans
- legislation.gov.uk: Building Act 1984, section 35C (stop notices)
- legislation.gov.uk: Building Act 1984, section 36
- Building Safety Regulator: Regulating the building control profession
- Salford City Council: Building regulations applications after 1 October 2023
- Colchester City Council: Building control fees and charges
- Crawley Borough Council: Building control questions and answers