What Happens If There’s No Party Wall Agreement? Disputes, Delays and Damage
November 10, 2026
Do Loft Conversions Need a Party Wall Agreement?
November 11, 2026To respond to a party wall notice, reply to your neighbour in writing within 14 days and choose one of three options: consent to the work, dissent (which starts the surveyor process), or do nothing. For most notices, doing nothing is treated as a dissent, so silence does not stop the work. It simply means a dispute is “deemed” to have arisen and surveyors will be appointed.
Below we explain what each option means, what to put in your reply, how counter-notices work and the timings that matter. If you have not yet decided whether to agree, our guide on whether you should consent to a party wall notice goes deeper into that decision.
What should you check as soon as the notice arrives?
Before you reply, read the notice carefully and work out which kind it is. The Party Wall etc. Act 1996 has three main types, and the rules are slightly different for each.
- Party structure notice (section 2): work to an existing shared wall, such as cutting in to take the bearing of a steel beam, raising the wall, underpinning or removing a chimney breast. At least two months’ notice is required.
- Line of junction notice (section 1): a new wall built on or at the boundary line. At least one month’s notice is required.
- Notice of adjacent excavation (section 6): digging within 3 metres of your building and deeper than your foundations, or within 6 metres where the dig would cut a 45-degree line from the bottom of your foundations. At least one month’s notice is required, with plans and sections.
Check that the notice names every owner of your property, gives the building owner’s name and address, describes the work clearly and states when it is due to start. The government’s explanatory booklet says a notice is only valid for a year, so a notice served for work that is many months away is worth querying. If you rent out the property or have a leasehold of more than a year, you may also count as an “owner” under the Act.
What are your 3 options when you receive a party wall notice?
The government’s explanatory booklet sets out the same three choices for every adjoining owner:
- Option 1, consent in writing. You agree to the work going ahead as described. No surveyors are needed, but the building owner still has to follow the Act, avoid unnecessary inconvenience and make good any damage.
- Option 2, dissent (refuse consent). This starts the dispute procedure. It does not stop the work. It means an impartial surveyor or surveyors will agree how the work is done through a document called a party wall award.
- Option 3, do nothing. For a party structure notice or an excavation notice, if you do not consent in writing within 14 days, you are treated as having dissented and a dispute is deemed to have arisen (section 5 of the Act). For a new wall astride the boundary under section 1, silence means the building owner must build wholly on their own land at their own expense.
In short, “do nothing” usually produces the same result as dissenting, just with less control over the process. It is better to reply.
How do you reply to a party wall notice?
Reply in writing and keep a copy. GOV.UK publishes ten example letters, including a “positive acknowledgement” and a “negative acknowledgement” for both party structure notices and 3/6 metre (excavation) notices. These are the simplest way to respond. Notices and replies can be sent by email, but only if both owners have agreed to that.
| Your choice | What your reply should say | What happens next |
|---|---|---|
| Consent | You consent to the works described in the notice | Work can start once the notice period ends (or earlier if you agree in writing) |
| Dissent, agreed surveyor | You dissent and agree to appoint the building owner’s surveyor (or another named surveyor) as the agreed surveyor | One surveyor prepares the award for both owners |
| Dissent, own surveyor | You dissent and appoint your own named surveyor | The two surveyors select a third surveyor and agree the award |
| No reply within 14 days | Nothing | Dispute deemed to arise (s2 and s6 notices); surveyors are appointed |
If you dissent but do not appoint a surveyor, section 10 of the Act lets the building owner ask you to do so. If you still have not appointed one within 10 days of that request, they can appoint a surveyor on your behalf. That surveyor still has to act impartially, but you lose the chance to choose who it is.
Should you choose an agreed surveyor or your own?
Whichever route you take, a surveyor appointed under the Act must act impartially and must not be one of the owners. The RICS consumer guide says sharing your neighbour’s surveyor as an “agreed surveyor” can reduce costs, but warns that once a surveyor is appointed they cannot be removed by the owner who appointed them. So choose carefully.
An agreed surveyor usually suits straightforward work, such as a steel beam bearing into a party wall for a loft conversion. Your own surveyor may make sense where the work is complex, such as underpinning or a deep excavation close to your house, or where you would simply feel more comfortable with someone you picked. RICS recommends using a surveyor with experience of party wall matters, and suggests looking for chartered (MRICS or FRICS) members.
On cost, the RICS guide says the surveyors’ fees normally fall on the building owner who served the notice. The exception is where you act unreasonably, for example by demanding pointless visits, or where work also benefits you, such as repairs to a shared defect. Our guide to party wall agreement costs covers typical fees.
What is a counter-notice, and when should you serve one?
A counter-notice lets you ask for extra or modified work for your own benefit while the builders are there. Under section 4 of the Act, for example, you can ask for chimney breasts, flues, piers or recesses to be built into the wall for your future use. The explanatory booklet says you may serve a counter-notice within one month of the original notice and should tell the building owner within 14 days if you intend to. The building owner must then respond within 14 days, or a dispute is deemed to arise. You would normally pay for the extra work you ask for.
How do you protect your property once you have replied?
Whether you consent or dissent, take these steps:
- Record the current condition of your property. The booklet says this is not a legal requirement but is “most prudent”, ideally with written notes and photographs. Without a record, it is harder to show later that damage was caused by the works. Where an award is made, it usually includes a schedule of condition.
- Read the award carefully. It is binding unless either owner appeals to the county court within 14 days of receiving it.
- Know your access rights and duties. You must let the building owner’s workers and surveyors in where necessary for work under the Act, after 14 days’ notice (except in an emergency).
- Raise damage promptly. The building owner must make good damage caused by the work or pay compensation, and later disputes can still go through the Act’s dispute process.
Is there anything specific to Essex and Suffolk?
No. The Party Wall etc. Act 1996 applies across England and Wales, so the process is the same in Colchester, Chelmsford or Ipswich as anywhere else. Councils do not administer it. The Planning Portal points out that it is a separate law from planning and building regulations, so a project can have planning permission and building control approval and still need party wall notices.
Frequently asked questions
How long do I have to respond to a party wall notice?
14 days from the day the notice was served. If you have not consented in writing by then to a party structure or excavation notice, you are treated as having dissented.
Can I stop the work by refusing to respond?
No. Silence or refusal does not stop lawful work under the Act. It triggers the dispute procedure, and surveyors decide how and when the work proceeds.
Do I have to pay for my own surveyor?
Usually not. RICS says surveyors’ fees normally fall on the building owner. You may have to pay if you act unreasonably or if the work also benefits you.
Can I change my mind after consenting?
Consent covers the work described in the notice. If the work later causes damage, the building owner still has to make it good, and that dispute can be dealt with under the Act. If the plans change significantly, a new notice may be needed.
Can I reply by email?
Yes, but only if you and the building owner have both agreed to use email for notices and documents.
Planning work next to a neighbour?
CJC Contracts is a Colchester-based building and groundworks contractor, established in 2007 and based in Great Horkesley. We work across Essex and Suffolk on extensions, groundworks and foundations and brickwork, and we plan party wall timings into our programmes from the start. For a free quote, get in touch online or call 01206 273689.