November 8, 2026To serve a party wall notice, you write to every adjoining owner, describe the work, give the date you plan to start, and deliver it by hand, by post, or by email if they have agreed to email. The timing is what keeps you legal: at least two months’ notice for work to an existing party wall, and at least one month for a new wall at the boundary or for excavating near your neighbour’s foundations. A notice lasts for one year, so serve it once your plans are firm, not years ahead.
Below is the step-by-step process under the Party Wall etc. Act 1996, which applies in England and Wales, with the timings, what a notice must contain and what happens after it lands. If you are still working out whether you need a notice at all, start with our guide to party wall agreements for extensions.
Which party wall notice do you need to serve?
The Act has three main types of notice, and each has its own notice period. Many extensions need more than one, for example a party structure notice for steel beams cut into the shared wall and a notice of adjacent excavation for the new foundations.
| Notice | Typical work | Minimum notice |
|---|---|---|
| Line of junction notice (section 1) | Building a new wall on or up to the boundary line | 1 month |
| Party structure notice (section 2) | Cutting in beams, raising, underpinning, repairing, demolishing and rebuilding, or cutting off projections from an existing party wall | 2 months |
| Notice of adjacent excavation (section 6) | Digging within 3 metres of a neighbour’s building and deeper than their foundations, or within 6 metres where the dig would cut a 45° line drawn down from their foundations | 1 month |
The government’s explanatory booklet says some very minor jobs, such as fixing shelves with plugs and screws, adding recessed sockets or replastering, may not need notice. The test is whether the work could affect the wall’s strength or support, or damage your neighbour’s side. If you are unsure, ask a qualified building professional before you assume you can skip it.
What must a party wall notice include?
There is no official form, but the GOV.UK booklet sets out what a valid notice should contain:
- Your name and address, naming every joint owner of your property.
- The address of the building where the work will be done, if it is different.
- A full description of the proposed work.
- The date you propose to start, which must not fall before the notice period ends.
- The date of the notice, ideally with a clear statement that it is a notice under the Party Wall etc. Act 1996.
- For excavation (section 6) notices: plans and sections showing where and how deep you will dig, and whether you propose to strengthen or safeguard the neighbour’s foundations.
GOV.UK publishes free template letters for each notice type, plus matching acknowledgement letters your neighbour can use to consent or dissent. Using them is the simplest way to make sure nothing is missed. A notice that leaves out a required detail can be challenged, which can push your start date back.
Who do you have to serve the notice on?
You serve every “adjoining owner”. Under the Act an owner is not just the person living next door. It includes the freeholder, a leaseholder with more than one year left on their lease, someone under contract to buy such an interest, and anyone entitled to receive the rent. One building can have several owners, so a converted house or block of flats next door may mean several notices.
Check the Land Registry title for the neighbouring property if you are not sure who owns it, and remember to name all joint owners of your own home on the notice too.
How do you deliver a party wall notice properly?
Section 15 of the Act lists the ways a notice can be served:
- By hand to the owner.
- By post to their usual or last known home or business address in the UK. For a company, to its registered or principal office.
- By email, but only if the owner has said they are willing to receive notices electronically and given you an address to use. This option was added on 6 April 2016.
- Addressed to “The Owner” if you don’t know the name, handed to someone at the property or, if it is empty, fixed to a conspicuous part of it.
Keep a copy of every notice and a record of how and when it was delivered. A dated photo of the hand delivery, or a proof of postage, can save an argument later about when the clock started.
What happens after you serve the notice?
Your neighbour can consent in writing, dissent, or do nothing. The booklet asks them to respond within 14 days.
- Written consent: the work can go ahead as notified. No surveyor is needed unless a dispute arises later, for example over damage. Your duties under the Act still apply.
- Dissent, or silence after 14 days: for party structure and excavation notices, a dispute is treated as having arisen. You then appoint either one “agreed surveyor” or a surveyor each, who will prepare a party wall award setting out how the work is done.
- Line of junction notices: if the neighbour does not consent in writing within 14 days to a wall built astride the boundary, you must build it wholly on your own land, at your own expense.
- Counter-notice: your neighbour has one month to serve a counter-notice asking for extra or modified work for their benefit, such as deeper foundations. You have 14 days to respond or a dispute is deemed to have arisen.
We explain the options in more detail in what happens if your neighbour refuses a party wall agreement, and typical surveyor costs in how much a party wall agreement costs.
When should you serve the notice to keep your build on schedule?
Work backwards from your start date. The notice period is a minimum, and if a dispute arises the surveyors still need time to inspect, agree a schedule of condition and draw up the award. A sensible timeline looks like this:
- Finalise drawings, including foundation depths and any steel bearings in the party wall, so the notice describes the real work.
- Talk to your neighbours first. The booklet and RICS both recommend this, as a notice out of the blue is more likely to be met with dissent.
- Serve notices at least two months before a party structure start, or one month for line of junction and excavation work. Allow longer if you expect a surveyor to be appointed.
- Wait for responses. Allow 14 days for consent or dissent, and up to one month for any counter-notice.
- Start within a year. A notice is valid for one year; if work hasn’t begun by then, you will need to serve again.
You can only start before the notice period ends if the adjoining owner agrees in writing. Planning permission and building regulations are separate processes and do not replace the party wall notice. Your builder will usually need the award before digging foundations or cutting into the shared wall. On our extension and groundworks projects, foundation design and party wall timing are planned together so the dig isn’t held up.
What if you don’t serve a party wall notice?
There is no criminal penalty or council enforcement for failing to serve notice. However, the GOV.UK booklet points out that a neighbour can go to court for an injunction to stop the work, or seek other legal redress. That can halt a site mid-build, with contractors still on the clock. Without a schedule of condition, it is also harder to show whether cracks next door were already there.
Frequently asked questions
Can I serve a party wall notice myself?
Yes. There is no requirement to use a surveyor or solicitor to serve notice, and GOV.UK provides template letters. Many homeowners still ask a party wall surveyor to prepare notices so the descriptions and drawings are correct.
Can I email a party wall notice?
Only if your neighbour has agreed to receive notices by email and given you the address to use. Otherwise, deliver it by hand or by post.
How long is a party wall notice valid?
One year. If the work has not started within that time, you will need to serve a fresh notice.
Does my neighbour have to reply?
No, but silence is not consent. For party structure and excavation notices, no written reply within 14 days means a dispute is treated as having arisen and surveyors must be appointed.
Planning an extension next to a neighbour?
CJC Contracts is a Colchester-based building and groundworks contractor, established in 2007 and based in Great Horkesley, working across Essex and Suffolk. We plan foundations, steelwork and build programmes around party wall timings so your project starts when it should. For a free quote, get in touch or call 01206 273689.