Is Building Control the Same as Building Regulations?
November 3, 2026
What Building Regulations Do I Need for an Extension?
November 4, 2026You should notify building control at least two days before any work starts on site, again within five days of the work reaching the legal “commenced” stage, before each key stage is covered up (normally with a day’s notice), and within five days of finishing. Miss these and the council can make you open up finished work for inspection, delay your completion certificate, or leave you with a building that’s hard to sell.
The rules apply whether you used a full plans application or a building notice with your local council. This guide sets out every notice, when it’s due and what happens if it’s missed. If you’re still working out what building control actually does, start with our guide to what building control is.
What notices does building control need, and when?
Since 1 October 2023 there have been two separate notices at the start of a job in England, as well as stage and completion notices. The Planning Portal and council guidance set out the timings as follows.
| Notice | When it’s due | What it’s for |
|---|---|---|
| Start (commencement) notice | At least 2 days before work begins | Tells the council work is about to start on site |
| Building work regarded as commenced notice | Within 5 days of reaching the legal commencement stage | Confirms the work has “commenced” so the approval doesn’t lapse |
| Stage inspection notices | In practice, at least one working day before each stage is covered | Lets an inspector see foundations, damp-proof course, oversite and drains before they disappear |
| Occupation before completion | At least 5 days before anyone moves in | Needed if you occupy before the work is finished |
| Completion notice | Within 5 days of finishing | Triggers the final inspection and completion certificate |
Your council’s approval letter or inspection plan will list the stages it wants to see for your project. Mid Suffolk and Babergh, for example, list up to 15 inspection types needing 24 hours’ notice, from foundations and drainage to roof structure, insulation and fire-stopping.
When should you tell building control you’re starting?
The first notice must reach the council at least two days before work starts. Salford City Council’s guidance is clear that work must not start until “at least two days have passed since the notice was given”. Most councils accept this online, by email or through the LABC app.
If you’ve chosen a building notice rather than full plans, Planning Portal guidance says work can start two days after the notice is submitted. Our guide to building notice vs full plans explains which route suits which projects.
What is the “work regarded as commenced” notice?
This second notice was added by Regulation 46A of the Building Regulations (inserted in 2023). It matters because a building regulations approval can lapse if work hasn’t legally “commenced” within three years. You must send it within five days of reaching the commencement stage, which is defined as:
- New houses and extensions: all foundations, the substructure, any basement and the ground floor structure are complete. Salford notes that “excavating foundation trenches alone will not normally be sufficient”.
- Complex buildings: the foundations and the lowest floor structure.
- Other building work: at least 15% of the overall work is complete.
The council can inspect, ask for information or reject the notice. If no rejection notice is issued within four weeks, the work is treated as commenced. For more on approvals lapsing, see how long building regs approvals last.
Which stages need an inspection before they’re covered up?
Neither start notice books an inspection. It is the responsibility of the person carrying out the work to request inspections at the right stages. The Planning Portal lists the core stages as:
- excavation for a foundation, before concrete goes in;
- the foundation itself;
- any damp-proof course;
- any concrete or other material laid over the site (the oversite);
- drainage, typically before and after backfilling.
Councils commonly add others, such as floor joists, steel beams, roof structure and insulation. Chelmsford City Council, for example, asks for 24 hours’ notice for all site inspections, runs them Monday to Friday between 9am and 3pm, and says requests after 3.30pm can’t be booked for the next working day. Plan your programme around that: a concrete lorry booked for 8am needs the trench inspection the day before.
On groundworks and drainage in particular, the timing of these visits drives the whole programme, because nothing can be poured or backfilled until the inspector has been.
What happens if you forget to notify building control?
According to the Planning Portal, if the council isn’t told about the relevant stages it “may, by notice in writing, require the work to be opened up for inspection”. In practice that can mean breaking out a floor slab, digging beside foundations or exposing drains, all at your cost.
Other knock-on effects include:
- No completion certificate. Chelmsford won’t issue one until it has been notified, carried out a final inspection and received any required documents. Mid Suffolk warns that a late completion notice may delay the certificate.
- Problems selling or remortgaging. Buyers’ solicitors routinely ask for completion certificates.
- Enforcement. Work that doesn’t comply can lead to enforcement action, as explained in our guide to whether building regs are a legal requirement.
- Lapsed approval. If the commencement stage isn’t reached and notified in time, the application may lapse.
If work has already been done without approval, the fix is usually a regularisation application to the council, which is more involved and expensive than doing it properly at the start.
Is it different with a private approver or a competent person?
Yes. If you use a registered building control approver instead of the council, the approver gives the council an “initial notice”. Under section 47 of the Building Act 1984, that notice comes into force when the council accepts it, and if the council doesn’t reject it within the prescribed period it’s treated as accepted. You then book inspections with the approver, following their inspection plan, rather than the council.
Some work, such as boiler installations, replacement windows and a lot of electrical work, can be self-certified by an installer registered with a competent person scheme. Southwark Council’s guidance says the installer, through the scheme provider, must provide evidence of compliance to the homeowner and the council “within 30 days of completing the work”. You don’t need to notify building control yourself for that item, but you should keep the certificate safe.
Who is responsible for notifying building control?
The legal duty sits with the person carrying out the building work, which on most projects is the builder. But under the dutyholder rules introduced in 2023, domestic clients also have responsibilities, and the consequences of missed inspections land on the property owner. Agree in writing who will send each notice and book each inspection before work starts.
A good contractor will build the inspection stages into the programme and hold off covering any work until it’s been signed off. That’s how we approach extensions and new builds across Essex and Suffolk.
Frequently asked questions
Can I start work the day after I submit a building notice?
No. You need to give at least two days’ notice before work starts, so plan for that gap.
Does digging the foundation trenches count as starting work?
Digging is starting work for the two-day start notice. But for the legal “commenced” stage on a house or extension, all the foundations, substructure and ground floor structure need to be complete.
How much notice do I need for a foundation inspection?
Most councils ask for 24 hours, or one working day. Check your inspection plan and book before the concrete is ordered.
When do I tell building control the work is finished?
Within five days of completion. The council will then carry out a final inspection and, if satisfied, issue a completion certificate.
Need a builder who handles building control properly?
CJC Contracts is a Colchester-based building and groundworks contractor, established in 2007 and based in Great Horkesley, working across Essex and Suffolk. We plan building control notices and inspections into every programme, so nothing gets covered up before it’s been checked. For a free quote, contact us online or call 01206 273689.