Are Building Regs a Legal Requirement? What Happens If You Ignore Them
November 2, 2026
When Should Building Control Be Notified? Avoid a Costly Retrospective Mess
November 3, 2026No. Building regulations are the legal standards that building work has to meet, covering things like structure, fire safety, drainage and insulation. Building control is the service that checks your work against those standards, either through your council or a private registered building control approver.
People use the two terms interchangeably because you can’t have one without the other: the regulations set the rules, and building control is how they’re applied to your project. Here’s who does what, and why the difference matters when you’re planning an extension or renovation.
What exactly are building regulations?
In England they’re the Building Regulations 2010, a statutory instrument made under the Building Act 1984. Schedule 1 sets out the functional requirements, such as making sure a building is structurally sound, resists the spread of fire, is properly drained and doesn’t waste energy. Breaking them is a criminal offence, which we explain in are building regs a legal requirement?
Alongside the regulations sit the Approved Documents, published by the government as statutory guidance on ways to comply. They run from Part A (structure) to Part T (toilet accommodation), plus Approved Document 7 on materials and workmanship. Following them is the usual way to show compliance, but the law allows other solutions if you can prove they meet the same requirement. Our plain-English guide to building regulations covers each part.
What is building control?
Building control is the independent checking process. A building control body examines your plans, inspects the work on site at key stages, such as foundations, drainage and the finished structure, and issues a completion certificate when it’s satisfied the work complies. For most domestic projects in England you can choose who does this:
- Local authority building control: your council’s own team.
- A registered building control approver (RBCA): a private business that must be registered with the Building Safety Regulator. You can check an approver on the regulator’s public register, which shows its registration number, the work it’s registered for and any conditions.
Higher-risk buildings (at least 7 storeys or 18 metres with two or more homes, plus hospitals and care homes) are different: the Building Safety Regulator itself is the building control authority for those.
How do building regulations and building control compare?
| Building regulations | Building control | |
|---|---|---|
| What it is | The legal standards for building work | The service that checks work against those standards |
| Where it comes from | Building Regulations 2010, made under the Building Act 1984 | Councils, registered approvers and, for higher-risk buildings, the Building Safety Regulator |
| What you deal with | Approved Documents, specifications and drawings | Applications, fees, inspections and a completion certificate |
| Who must comply | Everyone carrying out building work, plus dutyholders such as designers and contractors | You choose a building control body; only the council can enforce or approve work retrospectively |
Who enforces the building regulations?
For ordinary domestic work, enforcement sits with the local council. Since 1 October 2023 councils in England can serve compliance notices and stop notices, and they can still require non-compliant work to be altered or removed up to 10 years after completion. Councils are also the only body that can approve work retrospectively through regularisation.
A private approver checks and certifies work but doesn’t use those enforcement powers. If a project can’t continue with its approver, for example because the approver cancels its initial notice, the work reverts to the council. Colchester City Council’s guidance says that when an initial notice is cancelled the work becomes unauthorised and must normally revert to the local authority, and you pay for any opening up or remedial work needed. The GOV.UK reversion guidance adds that if a new approver isn’t in place within 7 days, the work automatically reverts.
Is building control the same as planning permission?
No, and this is the mix-up that catches out the most homeowners. Planning permission controls whether a development is acceptable: its use, size, appearance and effect on neighbours. Building regulations control how it’s built. Ipswich Borough Council’s guidance puts it simply: the two systems are separate, and a project may need both, with two applications and two fees.
That’s why an extension built under permitted development usually still needs building regs approval. Having one approval never covers the other.
What does the difference mean for your project?
In practice you design to the building regulations and get sign-off from building control. For a typical extension that means:
- Your designer prepares drawings and specifications that meet the regulations, with a structural engineer’s calculations where needed.
- You or your builder choose a building control body and submit a full plans application or building notice, as set out in our guide to building regulation approval.
- The builder notifies building control at each inspection stage.
- Parts such as boilers, electrics or windows may be self-certified by installers registered with a competent person scheme.
- You receive a completion certificate, which you’ll need when you sell.
Since October 2023 the regulations also set duties for clients, designers and contractors. As a homeowner your main duties are to share information about the property and cooperate with your team. The designer and contractor in charge carry the main responsibility for making sure the work complies.
Frequently asked questions
Is a building control officer the same as a building inspector?
Broadly, yes. Since April 2024, people working as building inspectors in England must be registered with the Building Safety Regulator, whether they work for a council or a private approver.
Do I have to use my council’s building control?
No. For work that isn’t on a higher-risk building, you can use your council or a registered building control approver. Retrospective approval is the exception, as only the council can give it.
What does building control actually inspect?
Typically the foundation excavations, the oversite and damp-proofing, drainage, structural elements such as steel beams, insulation and the completed work. The exact stages depend on the project and the building control body.
If I follow the Approved Documents, do I comply?
Following the relevant Approved Document can be relied on as tending to show you met the regulations, under section 7 of the Building Act 1984. Building control still needs to see the work built as designed.
Planning an extension in Essex or Suffolk?
CJC Contracts is a Colchester-based building and groundworks contractor, established in 2007 and based in Great Horkesley, working across Essex and Suffolk. We build extensions and new builds to the building regulations and work with council and private building control every week. Every project needs a site-specific quote, so request a free quote or call 01206 273689.
Sources
- GOV.UK: Building regulations approval
- GOV.UK: Approved Documents
- GOV.UK: Find a registered building control approver in England
- GOV.UK: Building control practice guidance, reversion FAQs
- legislation.gov.uk: Building Act 1984, section 7
- legislation.gov.uk: Building Act 1984, section 36
- Colchester City Council: Reversion application
- Ipswich Borough Council: Building regulations and planning permission
- Mid Suffolk District Council: Part 2A domestic client guide