What Is Building Regulation Approval and How Long Does It Take?
October 31, 2026
When Are Building Regs Required? The Jobs That Need Sign-Off
November 1, 2026Building regulations approval, whether a full plans approval or a building notice, lasts three years. If work hasn’t legally “commenced” within that time, the approval lapses and you’ll need to apply again. Once work has properly started it doesn’t expire, and a completion certificate has no expiry date once issued.
The catch is what “commenced” means. Since 1 October 2023, digging a trench or pouring a single footing is no longer enough in England. Here’s how long each stage lasts, what counts as starting and what happens if your approval runs out.
How long does each type of building regs approval last?
| Stage | How long it lasts | What ends it |
|---|---|---|
| Full plans approval (work not started) | 3 years from the application | Lapses if work hasn’t commenced |
| Building notice (work not started) | 3 years from when it was given | Lapses automatically if work hasn’t commenced |
| Approval once work has commenced | No time limit | Completion and sign-off |
| Completion certificate | No expiry date | Doesn’t expire |
| Council’s power to require removal of non-compliant work (section 36 notice) | Up to 10 years from completion | The 10-year limit |
The Planning Portal says a full plans approval is valid for three years from the date the plans were deposited, after which the council can declare it of no effect if the work hasn’t started. Mid Suffolk District Council’s guidance counts the three years from the date the application was validated. Either way, it’s worth checking the date on your own approval notice.
What counts as “commencing” work under building regs?
Regulation 46A of the Building Regulations 2010, added by the 2023 amendment regulations, sets out when work counts as commenced for the purpose of the three-year lapse rule. There are three tests:
- A new building or horizontal extension that isn’t complex: when the sub-surface structure is complete, including all foundations, any basement and the structure of the ground floor. This covers most house extensions and new homes.
- A complex building (one built on a shared foundation plinth or podium, with more than one storey below ground, or a public building for 100 or more visitors): when the foundations and the structure of the lowest floor are complete.
- All other building work, such as loft conversions or internal alterations: when the work that the client has described as 15% of the proposed work is complete. That statement is submitted with the application.
For a rear extension, that means the footings, oversite or floor slab and the ground floor structure all need to be in before the three years are up. It’s a much higher bar than the old “a spade in the ground” approach.
Do you have to tell building control when work has commenced?
Yes. There are now two separate notifications:
- At least two working days before work starts on site.
- No more than five days after the work reaches the commencement point above.
Cherwell District Council explains that if building control isn’t satisfied the work has commenced, it can reject the notice within four weeks, giving its reasons. Mid Suffolk’s guidance warns that failing to notify, or failing to commence within three years, will result in the application ceasing to have effect. In other words, building the foundations isn’t enough on its own. The commencement notice needs to go in too.
What happens if your building regs approval expires?
If the approval lapses, you’ll need to make a fresh application before starting. That means new fees and, importantly, the work will be assessed against the regulations in force at the time of the new application, which may be stricter than when you first applied.
Planning permission runs on its own clock. Most planning permissions must be started within three years too, but the rules on what counts as starting are different. Our guide How Long Does Planning Permission Last? covers that side.
Can new regulations affect a project that’s already approved?
Usually there are transitional arrangements, but they come with deadlines. The Future Homes Standard changes to Parts L and F come into force on 24 March 2027 for most building work. According to Forbes Solicitors’ summary of the regulations, for non-higher-risk work the previous rules continue to apply only if the application was submitted by 24 March 2027 and work commences on the relevant building by 24 March 2028.
If you’re planning a new home or a large extension and want to build under the current energy rules, both dates matter. Applying early won’t help if the foundations aren’t in on time.
Does a completion certificate ever expire?
No. Once issued, a completion certificate is permanent evidence that the building control body was satisfied the work complied. Keep it safe, because buyers’ solicitors will ask for it. Two time limits still matter after completion, though:
- Enforcement: under section 36 of the Building Act 1984, the council can require non-compliant work to be removed or altered. In England that notice can now be given up to 10 years after the work was completed.
- Regularisation: if work was done without approval, councils can only issue a regularisation certificate for work carried out after 11 November 1985.
If you’re buying an older property, our post When Did Building Regulations Come Into Force? explains why the date of the work matters.
What does this mean for projects in Essex and Suffolk?
The same national rules apply across both counties. Mid Suffolk District Council’s guidance, for example, applies the new commencement definitions to applications submitted after 1 October 2023. It requires notification within five days of reaching the commencement level and says the first inspection is usually at foundation or drainage stage. If you got approval two or three years ago and haven’t started, check the date now. Getting the groundworks in place in time is often what keeps an approval alive.
Frequently asked questions
Do building regs last forever once work has started?
Yes. Once work has commenced under the legal definition and you’ve notified building control, the approval doesn’t lapse, even if the build takes several years. You still need inspections and a final sign-off to get a completion certificate.
Can I extend a building regulations approval?
The three-year limit comes from the Building Act and the 2023 regulations, so don’t count on getting more time. If work won’t commence within three years, plan on submitting a new application, and speak to your building control body early.
Does a building notice last as long as full plans approval?
Yes. A building notice also lasts three years and lapses automatically if work hasn’t begun by then.
How long does it take to get building regs approval in the first place?
For a full plans application, the council must decide within five weeks or, with your agreement, up to two months. Our guide What Is Building Regulation Approval and How Long Does It Take? walks through each route.
Need the groundworks in before your approval runs out?
CJC Contracts is a Colchester-based building and groundworks contractor, established in 2007 and based in Great Horkesley, working across Essex and Suffolk. We carry out groundworks and foundations and build extensions and new builds. Every project needs a site-specific quote, so request a free quote or call 01206 273689.
Sources
- Building Regulations etc. (Amendment) (England) Regulations 2023, regulation 15 (new regulation 46A)
- Planning Portal: Full plans
- Cherwell District Council: Commencing work
- Mid Suffolk District Council: Commencement of work
- Building Act 1984, section 36
- Forbes Solicitors: Future Homes Standard implementation timetable
- Epping Forest District Council: Regularisation