The St Leonards project brought together drainage access, local excavation, surface preparation and paving repairs around an established building. The work took place in narrow side areas and alongside parking, with temporary barriers and protection defining the construction zones.
The full sequence is much more informative than a few finished paving views. It shows the opening-up, rubble removal and concealed drainage details that had to be dealt with before the external surfaces could be reinstated.
Creating access to the below-ground work
The early photographs show protected wall faces, a compact excavator and narrow working strips beside the building. Existing surfaces are removed in places to expose the construction below, while materials and equipment have to fit within a constrained access route.
That setting affects the order of work. Spoil needs to be removed without blocking the next operation, and retained walls, windows and services need protection while excavation and breakout take place nearby. The prepared routes then provide access for the drainage and reinstatement stages.
Inspecting chambers and service details
The gallery includes opened chambers and exposed pipework at the base of the building. These photographs record the point at which connections can be inspected and local repairs defined before the ground is closed again.
Chamber frames and drainage inlets also need to be coordinated with the eventual paving level. If that relationship is left unresolved, a completed surface may have to be disturbed again to correct an awkward cover or connection.
Rebuilding the external surfaces
Later photographs show prepared ground and new slabs fitted around the frontage. The paving meets the building, kerb and retained surface, requiring accurate levels and deliberate cuts at the edges.
The supporting layers beneath the slabs are central to the result. A consistent bed helps prevent rocking or settlement, while the finished profile needs to suit the intended route and drainage arrangement. Local reinstatement also has to connect cleanly to adjacent panels that remain in place.
A coordinated external repair package
The broader site views show how the work relates to parking spaces, entrances and side passages. Those areas remain part of the construction problem throughout, influencing temporary access and the protection of completed sections.
The gallery follows St Leonards from opening-up to visible paving reinstatement. It demonstrates the value of treating drainage, groundwork and surface repairs as connected operations rather than separate small jobs.
CJC undertakes drainage installation and repairs in Essex and Suffolk, from individual repairs to wider construction packages.
ON SITE · IN DETAIL
Project gallery
Project setting, working details and the construction stages available in the archive.
24 photographs · Select a photograph to enlarge it.
01 / 24Enlarge
02 / 24Enlarge
03 / 24Enlarge
04 / 24Enlarge
05 / 24Enlarge
06 / 24Enlarge
07 / 24Enlarge
08 / 24Enlarge
09 / 24Enlarge
10 / 24Enlarge
11 / 24Enlarge
12 / 24Enlarge
13 / 24Enlarge
14 / 24Enlarge
15 / 24Enlarge
16 / 24Enlarge
17 / 24Enlarge
18 / 24Enlarge
19 / 24Enlarge
20 / 24Enlarge
21 / 24Enlarge
22 / 24Enlarge
23 / 24Enlarge
24 / 24Enlarge 