CONSTRUCTION GUIDE · Steelwork
Opening up a wall: the beam is only part of the job
Published · Reviewed 17 September 2026

Creating an open-plan space is often described as taking out a wall and putting in a beam. That shorthand leaves out much of the work that determines whether the alteration can be built smoothly. Existing construction, support during the work, bearing details and the final finish all need to be coordinated before demolition starts.
Establish what the wall is doing
The structural designer needs to understand the building rather than infer it solely from room layout. Walls may support floors, roofs or other walls, and earlier alterations can change the expected arrangement. Opening-up investigations may be needed to verify concealed construction before the design is completed.
HSE states that structural alteration must be planned and carried out by competent people to avoid unplanned collapse. Its guidance on structural stability during alterations is relevant to the sequence as well as the finished structure. A visual impression that a wall looks lightweight is not an adequate basis for removal.
Coordinate the whole load path
The beam, its end supports and the construction below those supports form one system. Ask the designer to explain any required investigations or strengthening, and ensure the builder receives the full details. A beam size on a sketch does not resolve every connection or bearing condition.
Discuss headroom and finished appearance at the same time. A downstand beam may affect kitchen units, lighting and ceiling lines. If the intention is to conceal it, that may change the design and work involved. Resolve the preference before the steel is fabricated rather than trying to hide an unexpected detail later.
Plan access and the temporary stage
Consider how the steel will enter the building and be installed. Door widths, occupied rooms, floor protection and lifting arrangements can affect the method. Temporary support needs its own suitable design and coordination; it should not be improvised from the permanent beam calculation.
Trace services before opening the wall. Electrical cables, heating pipes and other concealed services may require isolation or alteration by the appropriate trades. Schedule those activities so structural work does not become dependent on an unplanned emergency visit.
Include protection and making good
The required fire protection, finishes and inspection arrangements should be specified for the actual project. Allow for disturbed ceilings, wall junctions, skirtings, flooring and decoration. The visible opening may be a small part of the room, but matching existing finishes can extend the area that needs attention.
Confirm which building control approvals and inspections apply, and retain the engineering information and completion records. Structural design, building control and any relevant party wall process serve different purposes; one should not be assumed to replace the others.
When enquiring about structural steelwork, provide the existing layout, proposed opening, engineering information and access constraints. This helps CJC discuss the construction as a complete alteration, including the work required to leave the surrounding space ready for use.
Guidance reviewed on 17 September 2026. Requirements and suitable construction details depend on the property and project; follow the applicable regulations and your appointed specialists’ advice.