Lift shaft construction: reinforced concrete at height

From the CJC project archivePublished

Crane lifting a concrete skip above lift-shaft formwork and scaffold platforms

This reinforced concrete lift shaft is one of the most striking construction sequences in the CJC archive. A crane raises a concrete skip above the upper formwork, while the completed lower walls stand within a scaffold and working-platform arrangement. The photographs capture the point where ground-level construction becomes a carefully coordinated operation at height.

The shaft has a compact footprint, but several systems have to work together: the permanent concrete walls, the reinforcement for the next lift, the shutters that define the new wall section and the access needed to place the concrete accurately.

Building the shaft in vertical stages

The exposed lower concrete shows the shaft already rising through several metres of height. Above it, the next section remains enclosed in timber-faced formwork, with reinforcement visible at the top. This illustrates the staged nature of the construction: complete one lift, prepare its connection and then form the next.

The position of the shaft needs to remain consistent as it rises. Wall alignment, internal dimensions and openings all have to follow the design so that the eventual lift installation can be accommodated. Small setting-out errors at the base would otherwise carry upwards through the structure.

Formwork, reinforcement and working access

The upper shutters are held by a system of supporting members and braces. Around them, scaffold platforms create access to the work faces and to the placing position. These temporary elements have to suit the geometry of the shaft while allowing the concrete operation to proceed.

Before a lift is poured, the reinforcement and any embedded details need to be checked while access is still available. The shutters establish the finished wall thickness and face, so their line, stability and joints directly influence the concrete left behind after striking.

Crane-assisted concrete placement

The lead photograph shows a suspended skip with a delivery chute positioned over the shaft. This method brings concrete to a location that cannot be reached by a normal ground-level placing operation. The team at the top coordinates the delivery with the work inside the forms.

The lifting and placing sequence needs to be planned around the load, the crane position, the access platforms and the formwork design. Communication between the lifting operation and the placing team is central. Concrete then has to be distributed and compacted through the wall section without losing control of the intended pour rate or disturbing the reinforcement.

Preparing the next lift

After placing, the concrete needs to develop sufficiently for the next operations to proceed in the specified order. Formwork removal, inspection and preparation of the following lift are all linked to that sequence. The visible construction joints on the lower shaft help explain how successive stages become one permanent structure.

The four photographs cover: the placing operation, closer views of the upper work and the wider site context. Together they show the planning and coordination behind a concrete structure that is much more demanding than its compact footprint suggests.