What Is Permitted Development? The Rules That Let You Extend Without Planning
October 15, 2026
Planning Application Checklist: Documents to Prepare Before You Submit
October 19, 2026To get planning permission in England, you submit a planning application to your local council, usually online through the Planning Portal, with drawings, forms and a fee. For a householder extension the fee is currently £548, and most applications are decided within 8 weeks. The secret to a smooth approval is preparation: checking whether you need permission at all, getting good drawings, and designing something that fits the council’s local policies.
Here is the process step by step, from first idea to the day you can start building.
Step 1: Do you actually need planning permission?
Many home extensions, loft conversions and outbuildings can be built under permitted development, without a planning application. Our guide to what permitted development is explains the size limits. You will usually need planning permission if your project goes beyond those limits, if you live in a flat or listed building, or if your home is in a conservation area or another protected area.
If you are unsure, ask your council. If you want written certainty that a project does not need permission, you can apply for a Lawful Development Certificate instead.
Step 2: Should you get pre-application advice?
Most councils offer pre-application advice, usually for a fee. A planning officer looks at your outline proposal and tells you whether it is likely to be supported and what would need to change. It is optional, but for anything unusual, in a conservation area or close to neighbours, it can save you from paying for a full set of drawings that later gets refused.
It is also worth talking to your neighbours early. The council will notify them once you apply, and objections are easier to deal with before plans are fixed.
Step 3: What drawings and documents do you need?
The Planning Portal sets out the national requirements every valid application must include:
- Application form – the householder form for extensions and alterations to a house.
- Location plan – a map showing the site and its surroundings, with the site outlined in red.
- Site plan (block plan) – showing the proposed work in detail in relation to the boundaries.
- Ownership certificate – confirming who owns the land, and that any other owners have been notified.
- Agricultural holdings certificate – required whether or not farmland is involved.
- The correct fee.
In practice you will also need existing and proposed floor plans and elevations, and each council publishes its own local validation list. That might ask for a design and access statement in a conservation area, a heritage statement for a listed building, a tree survey, or a flood risk assessment. Check your council’s list before you submit, because missing documents are the most common reason applications are held up at the start.
Step 4: How much does a planning application cost?
Planning fees in England are set nationally and rose on 1 April 2026. These are the current fees for the most common home projects:
| Application type | Fee (from 1 April 2026) |
|---|---|
| Householder application (extension or alteration to one house) | £548 |
| Prior approval for a larger rear extension | £249 |
| Lawful Development Certificate (proposed work) | Half the normal planning fee |
| Discharge of conditions (householder) | £89 |
| New houses (up to 10) | £610 per house |
The council fee is only part of the cost. Budget for drawings from an architect or designer, any surveys your council asks for, and the Planning Portal’s small service charge if you apply online.
Step 5: What happens after you apply?
- Validation. The council checks you have sent everything it needs. If something is missing, the clock does not start until you supply it.
- Consultation. The council notifies neighbours, often with a site notice, and may consult highways, conservation or tree officers. People usually have 21 days to comment.
- Assessment. A planning officer visits or reviews the site and judges the plans against the local plan: size, design, the effect on neighbours’ light and privacy, parking and the character of the area.
- Decision. GOV.UK says most applications are decided within 8 weeks, or 13 weeks for unusually large or complex ones. Most householder applications are decided by officers rather than a committee.
What if your planning application is refused?
Read the refusal reasons carefully. Often the simplest route is to amend the design to deal with the objections and reapply. You can also appeal to the Planning Inspectorate. For a refused householder application, GOV.UK says you normally have 12 weeks from the date on the decision letter, and less if an enforcement notice has been served. You can also appeal if the council fails to decide within the time limit.
You have planning permission: what next?
Read the conditions on your decision notice. Some must be met before work starts, such as approving materials, and these need a separate discharge of conditions application. Planning permission normally lasts three years, so work must begin within that time.
Planning permission is not the only approval you need. The build must also meet the Building Regulations and be signed off by building control, and work on or near a shared wall may need a party wall notice. This is the point to get detailed construction drawings, structural calculations and builders’ quotes.
What should you know about planning in Essex and Suffolk?
Each district council, such as Colchester, Braintree, Tendring or Babergh and Mid Suffolk, has its own local plan and design guidance. Large parts of the area are conservation areas or sit within protected landscapes like the Dedham Vale National Landscape, where design and materials are judged more closely. Search your council’s planning register for similar approved schemes on your street: they are a useful guide to what officers will support.
Frequently asked questions
Can I apply for planning permission myself?
Yes. Anyone can submit an application, including the homeowner. Most people use an architect or designer for the drawings, because clear, accurate plans make approval far more likely.
How long does planning permission take?
Most decisions are made within 8 weeks of the application being validated. Add time beforehand for drawings, surveys and any pre-application advice.
Can I start building before planning permission is granted?
You can, but it is a risk. If permission is refused, the council can take enforcement action and require the work to be removed.
Do my neighbours get a say?
Neighbours are notified and can comment, but the council decides on planning grounds, not on the number of objections.