The Paddington project involved substantial structural work within and around an existing building. Excavation, new concrete bases, reinforced walls, steelwork and supported floor construction appear throughout the sequence, with the street frontage and retained masonry illustrating the constrained setting.
This is a project where the construction order is central to the story. New work has to be introduced while retained elements remain supported, and the available space changes as the structure develops.
Opening up and establishing levels
The photographs record excavated areas, stripped internal spaces and surveying equipment set up within the work. Establishing reliable levels is particularly important when new concrete has to connect to an existing building with several retained reference points.
Excavation and opening-up reveal the construction that the new work must meet. Those observations inform the next stage, including the positions of foundations, wall starts and any local changes needed at the interface. Access for plant and removal of spoil also has to fit the narrow site.
Forming new concrete bases and walls
Fresh concrete bases carry projecting reinforcement beside the exposed ground and retained structure. Later images show wall cages and timber forms, including a curved reinforced section. These details demonstrate that the concrete footprint was shaped to the particular building rather than assembled as a simple rectangle.
The reinforcement needs to connect through the base and wall sequence, while the forms establish thickness, line and openings. Before a wall is closed up for pouring, the interfaces and any embedded details need to be checked while they remain accessible.
Coordinating steelwork and supported floors
The interior construction includes steel beams alongside closely spaced temporary supports and timber deck formwork. Some photographs look directly beneath the assembly, showing how the new floor construction is carried during the work.
Temporary support, retained masonry and the new permanent frame have different roles, but their sequence is interdependent. Removing or altering one part requires the intended support path to be established first. The photographs make that complexity visible without requiring a finished-room view to explain the scale of the work.
Building within a constrained urban site
The wider views place the excavation close to neighbouring buildings and the street. Materials, plant and operatives share a limited working area, making coordination and preparation especially valuable.
The gallery follows the structural work through its main recorded stages: opening-up, new bases, reinforcement, wall forms and supported floors. It gives Paddington a fuller account of the engineering and site organisation behind alterations that would largely disappear beneath the final finishes.
For a similar project, find out about our building repairs and renovations in Essex and Suffolk.
ON SITE · IN DETAIL
Project gallery
Opening-up, concrete bases, reinforcement and supported floors.
23 photographs · Select a photograph to enlarge it.
01 / 23Enlarge
02 / 23Enlarge
03 / 23Enlarge
04 / 23Enlarge
05 / 23Enlarge
06 / 23Enlarge
07 / 23Enlarge
08 / 23Enlarge
09 / 23Enlarge
10 / 23Enlarge
11 / 23Enlarge
12 / 23Enlarge
13 / 23Enlarge
14 / 23Enlarge
15 / 23Enlarge
16 / 23Enlarge
17 / 23Enlarge
18 / 23Enlarge
19 / 23Enlarge
20 / 23Enlarge
21 / 23Enlarge
22 / 23Enlarge
23 / 23Enlarge 