November 1, 2026Building regulation approval is confirmation from a building control body, either your council’s building control team or a private registered building control approver, that your project meets the Building Regulations 2010. These are the national minimum standards for structure, fire safety, drainage, ventilation, energy efficiency, access and more. With a full plans application the council must decide within five weeks, or up to two months if you agree to an extension. With a building notice, work can start after giving two working days’ notice, but your plans aren’t approved in advance.
Approval isn’t a single stamp. It runs from the application, through site inspections, to a completion certificate at the end. Here’s how each stage works and how long it realistically takes.
What does building regulation approval actually cover?
Building regulations deal with how a building is built, not whether it should be built at all. That second question belongs to planning permission, which is a separate consent with its own process. A typical extension often needs both, and having one doesn’t give you the other. Our guide What Are Building Regulations? explains the technical parts of the regulations in plain English.
According to GOV.UK, for work that isn’t on a higher-risk building you can choose either your local authority or a private registered building control approver. Higher-risk buildings (at least 7 storeys or 18 metres high, with at least 2 residential units, or hospitals and care homes of that height) go to the Building Safety Regulator instead. If you use an installer registered with a competent person scheme, for example for some electrical, heating or window work, you don’t need to apply for approval yourself, because the installer self-certifies the work.
What are the ways to get building regulation approval?
There are four main routes. The right one depends on the size of the job, how much certainty you want before you start and whether the work has already been done.
| Route | What you submit | When work can start | Best suited to |
|---|---|---|---|
| Full plans application | Detailed drawings and construction information | After giving notice; ideally once plans are approved | Extensions, loft conversions, new homes and anything structural |
| Building notice | A notice and basic information, with no detailed plans approved | After giving notice, usually two working days | Small, simple residential jobs |
| Private approver (initial notice) | An initial notice sent to the council by your approver | Once the initial notice is in place | Projects where you’d prefer a private approver to the council |
| Regularisation | An application for work already carried out | Work is already done | Unauthorised work completed after 11 November 1985 |
Councils note that a building notice can only be used for residential work. It can’t be used for any extension or development within 3 metres of a public sewer, which rules it out for many rear extensions. Regularisation is only available through the council, not a private approver.
How long does a full plans application take?
The Planning Portal says the council must give its decision within five weeks of the plans being deposited or, if you agree, within a maximum of two months. That extra time is often used to resolve queries about structural calculations, drainage or insulation details.
The decision can be one of three things:
- Approval: the plans comply as submitted.
- Conditional approval: the plans are approved subject to modifications or further plans. Conditions can only be added if you asked for them or agreed in writing.
- Rejection: the notice must give the reasons, so the drawings can be amended and resubmitted.
You can legally start work before the plans are approved, as long as you’ve given notice. The risk is that if the approved plans differ from what you’ve built, the work may have to be altered or removed. For anything structural, most builders and clients prefer to wait for the approval notice. It also gives your contractor a firm set of details to price and build from.
How quickly can you start with a building notice?
A building notice is designed to get small jobs under way quickly. You give the notice, then tell building control at least two working days before work starts. There’s no plan approval, so the inspector checks the work as it goes. If something doesn’t comply, it has to be put right at your expense.
That speed comes at a price in certainty. Without approved plans, you’re relying on the builder and the inspector agreeing on the details on site. That’s fine for straightforward work. It’s much riskier for steel beams, new foundations or anything near drains.
What notices and inspections happen during the build?
Since 1 October 2023, the notification rules in England have been stricter. Councils such as Cherwell set out the sequence:
- Before starting: give at least two working days’ notice that work is about to begin (five working days for higher-risk buildings).
- Commencement: notify building control no more than five days after the work reaches the legal definition of “commenced”. For a new building or extension, that’s when the foundations and ground floor structure are complete.
- Inspections: the inspector visits at key stages, usually foundations and drainage first, then structure, insulation and so on.
- Completion: tell building control within five days of finishing so the final inspection can be booked.
Our post What Is Building Control? explains what inspectors look for and the powers they have if work doesn’t comply.
When do you get the completion certificate?
The completion certificate is the document that matters when you sell or remortgage, because it shows the work complied with the regulations. With a full plans application you should ask for one when you first apply, and the Planning Portal says the council will issue it once it is satisfied the completed work complies. Designing Buildings notes that this should normally happen within eight weeks of completion. Councils also issue completion certificates for building notice work after a satisfactory final inspection.
Delays usually come from missing paperwork rather than the inspection itself: electrical certificates, SAP or energy calculations, air tightness results or drainage test results. Keeping these together as the job goes on saves weeks at the end.
What does this mean for projects in Essex and Suffolk?
The process is the same across England, but local details still matter. Each council sets its own building control fees: Colchester City Council publishes a schedule covering extensions, loft conversions and new homes, which we break down in How Much Does Building Regulations Cost? If a public sewer runs through your garden, building within 3 metres of it rules out a building notice and means talking to Anglian Water, the sewerage company for most of the region, about building over or near the sewer. That’s best sorted before your full plans application goes in.
For larger housing schemes, the Building Safety Levy now applies to building control applications submitted on or after 1 October 2026 for developments of 10 or more homes. It doesn’t apply to schemes of fewer than 10 dwellings.
Frequently asked questions
Is building regulation approval the same as planning permission?
No. Planning permission decides whether a development is acceptable in principle and how it looks. Building regulation approval covers how it’s constructed. Many projects need both, and some permitted development works still need building regulations approval.
How long is building regulation approval valid for?
Three years. If the work hasn’t commenced within that time, the approval lapses and you’ll need to apply again. Once work has properly started, it doesn’t expire.
Can I start work while my full plans application is being checked?
Yes, after giving at least two working days’ notice. But if the approved plans need changes, anything already built that doesn’t comply may have to be altered or removed.
What if work was done without building regulation approval?
For work carried out after 11 November 1985, you can apply to the council for a regularisation certificate. The inspector may ask for parts of the work to be opened up so they can check it.
Planning an extension or new build?
CJC Contracts is a Colchester-based building and groundworks contractor, established in 2007 and based in Great Horkesley, working across Essex and Suffolk. We build extensions and new builds, and carry out the drainage work inspectors check first. Every project needs a site-specific quote, so request a free quote or call 01206 273689.
Sources
- GOV.UK: Building regulations approval
- Planning Portal: Full plans
- Cherwell District Council: Building notice application
- Cherwell District Council: Commencing work
- Designing Buildings: How long it takes to get building regulations approval
- Southend-on-Sea City Council: Building Safety Levy
- Epping Forest District Council: Regularisation