What Do I Need Planning Permission For? The UK Checklist to Bookmark
October 23, 2026
How Long Does Planning Permission Take in the UK? Realistic Timelines
October 24, 2026For most homeowners, a retrospective planning application takes about 8 weeks from the date the council validates it. That’s the same statutory target as any other householder application. Allow 10 to 16 weeks in practice once validation, consultation and any agreed extension of time are added, and longer if you end up at appeal. Approval isn’t guaranteed. The council judges the work on its planning merits as if it hadn’t been built yet, and if it refuses, it can serve an enforcement notice requiring you to put things back as they were.
This guide covers England. Wales, Scotland and Northern Ireland have their own systems.
What is retrospective planning permission?
Retrospective planning permission (sometimes called a “Section 73A” application, after the section of the Town and Country Planning Act 1990 that allows it) is permission for development that has already been carried out without the consent it needed. Typical examples are an extension that went beyond permitted development limits, a garden building used as living space, a raised patio, or a fence that’s taller than allowed.
Building without permission isn’t a criminal offence in itself. It becomes an offence if the council serves an enforcement notice and you don’t comply with it. A retrospective application is the usual way to put things right, and councils often invite one when they first contact you about a breach.
How long does a retrospective application take, stage by stage?
Retrospective applications follow the same process and deadlines as a normal application. Under national rules, councils should decide most applications within 8 weeks of validation, and major developments within 13 weeks. If they need longer, they can ask you to agree an extension of time in writing.
| Stage | Typical time | What happens |
|---|---|---|
| Preparing the application | 1–4 weeks | Measured drawings of what’s actually been built, a site plan, forms and the fee. Longer if you need surveys or a planning consultant. |
| Validation | Days to a few weeks | The council checks everything is there. The 8-week clock only starts once the application is valid. |
| Consultation | At least 21 days (within the 8 weeks) | Neighbours are notified and can comment. In a retrospective case they can see exactly what’s been built. |
| Decision | 8 weeks from validation (13 for major) | Officer report and decision, or a committee decision if the case is called in. |
| Extension of time | Often a few weeks | Only if you agree it in writing. Government policy says non-major applications shouldn’t take more than 16 weeks unless a longer period is agreed. |
| Appeal (if refused) | Several months | Decided by the Planning Inspectorate. Strict deadlines apply, as explained below. |
If a valid application isn’t decided within the statutory period or an agreed extension, you can appeal against non-determination. If it’s still undecided after 16 weeks for a non-major application (and you haven’t agreed longer or appealed), the fee should be refunded.
Will you get retrospective planning permission?
There’s no special test for retrospective applications. Government guidance says they must be considered “in the normal way”, against the local plan and national policy, exactly as if you’d applied before building. Councils also make the point the other way round: Buckinghamshire Council, for example, tells applicants that “the fact that work has already been carried out will not influence our decision”. Having already spent the money doesn’t count in your favour.
In practice, your chances depend on the same issues that decide any application:
- Impact on neighbours: loss of light, overbearing bulk and overlooking are the most common reasons for refusal.
- Design and appearance: whether the work suits the house and the street.
- Protected areas: conservation areas, National Landscapes and listed buildings face stricter tests. Unauthorised work to a listed building is a separate and more serious matter.
- Policy: whether the work fits the council’s local plan, for example on outbuildings or changes of use.
Work that only slightly exceeds permitted development limits and causes no real harm often has a good chance. Work that a neighbour has complained about, or that would have been refused had you applied first, is much less likely to succeed. Our guide to mistakes that get applications refused covers the issues officers look at.
How much does a retrospective application cost?
There’s no separate retrospective fee in England. You pay the normal national fee for the type of application. For an extension or alteration to a single house, that’s £548 from 1 April 2026. Ministers have been asked to set a higher fee for retrospective applications, but the government’s July 2026 response to the fees consultation didn’t take that forward, so check the Planning Portal fee calculator before you apply.
The fee is rarely the biggest cost. Measured drawings, any specialist reports and, if the application fails, the cost of altering or removing the work usually matter far more.
What happens if retrospective permission is refused?
The council can issue an enforcement notice requiring you to change or remove the work. You have three main options:
- Appeal the refusal. For a householder application you normally have 12 weeks from the decision letter. If an enforcement notice was served in the two years before the refusal, the deadline drops to 28 days.
- Appeal the enforcement notice. This must usually reach the Planning Inspectorate within 28 days of the notice being served, and before it takes effect. Since 25 April 2024 you generally can’t appeal on the ground that permission should be granted (ground (a)) if the notice follows a related retrospective application that was refused within the previous two years.
- Comply or submit a revised scheme. A smaller or redesigned version that addresses the reasons for refusal is often the quickest way out.
Ignoring a notice once the compliance period has passed is a criminal offence with an unlimited fine on conviction, and the court can also take account of any financial benefit you gained.
Can you just wait until it’s too late for enforcement?
Not for anything built recently. Before 25 April 2024, building work became immune from enforcement four years after it was substantially completed. For work substantially completed on or after that date, the limit is now 10 years, the same as most changes of use. Councils can also act beyond those limits where a breach has been deliberately concealed.
Unauthorised work also causes problems when you sell or remortgage, because buyers’ solicitors ask for planning and building control paperwork. If you believe older work is already immune, you can apply for a Lawful Development Certificate to confirm it rather than making a retrospective application.
What about building regulations?
Planning permission and building regulations are separate. If the work also needed building regulations approval and didn’t get it, you can apply to your council’s building control for a regularisation certificate, which covers work started on or after 11 November 1985. Be prepared for the inspector to ask for parts of the work to be exposed, altered or removed so they can check foundations, structure, insulation and drainage.
Frequently asked questions
Is retrospective planning permission harder to get?
Legally, no. It’s assessed on the same planning merits as any application. In practice, cases often reach the council because a neighbour has complained, which tends to mean objections are already on the table.
Can I keep using the building while the application is decided?
Usually, yes, unless the council has served a stop notice or temporary stop notice. Councils in England can now issue temporary stop notices lasting up to 56 days while they investigate.
Do I have to apply if the council hasn’t contacted me?
No one forces you to, but applying voluntarily gives you control over the timing and can avoid problems when you sell. It’s usually better than waiting for a complaint.
Can I apply for retrospective permission while an enforcement notice is in force?
You can submit one, but the council can decline to determine a retrospective application for development already covered by an enforcement notice. Get advice quickly, as the appeal deadlines are short.
Need work put right? Talk to CJC Contracts
CJC Contracts is a Colchester-based building and groundworks contractor, established in 2007 and based in Great Horkesley, working across Essex and Suffolk. If a retrospective application asks for changes, or you’re planning a new project and want it done properly first time, we can help with extensions and building repairs and alterations. Get a free quote or call 01206 273689.
Sources
- Retrospective planning permission – Planning Portal
- Enforcement and post-permission matters – GOV.UK
- Determining a planning application – GOV.UK
- Appeal a householder planning decision – GOV.UK
- Enforcement appeals – Planning Portal
- The Levelling-up and Regeneration Act 2023 (Commencement No. 4 etc.) Regulations 2024 – legislation.gov.uk
- Fees for planning applications: government response – GOV.UK
- Planning application fees from April 2026 – Horsham District Council
- Apply for retrospective planning permission – Buckinghamshire Council
- Regularisation application – London Borough of Barking and Dagenham